Item 27.17
Protective top cover
Considering for 1 job
(a) 150 mm dia and 4 mm
thick M.S. pipe 1 meter @ 1600 Per meter = 1600
(b) 4 mm thick 200 mm dia plate 1 No. @ 850 each = 850
(c) Welding and other cost as necessary L.S. = 150
Total = 2600
Profit 0.1 = 260
Overhead 0.035 = 91
= 2951
Add VAT with adjustment factor 1.04712 0.045 = 139.05
Grand total = 3090.05
Say, 3090 .00 each