Item 27.3.8
Supplying, fitting fixing tube-well log describing technical information of the tube-well as
per instruction and direction of the engineer in charge.
Considering 1 No.
(a) Cost of plate/pillar 1 No. @ 560 each = 560
(b) Cost of writing information L.S. = 480
(c) Cost of fittings and labour for erection or fitting, fixing etc. L.S. = 320
Total = 1360
Profit 0.1 = 136
Overhead 0.035 = 47.6
= 1543.6
Add VAT with adjustment factor 1.04712 0.045 = 72.74
Grand total = 1616.34
Rate each. = 1616.34
Say, 1616 .00 each.