Item 27.3.9
Filling the top 0.6 meter of the bore hole around the top pipe with a sanitary seal of concrete
of proportion (1:2:4):
0.24 cft. 131.65 Per cft. = 31.6
Profit 0.1 = 3.16
Overhead 0.035 = 1.11
= 35.87
Add VAT with adjustment factor 1.04712 0.045 = 1.69
Total = 37.56