Item 27.30
Long term pumping test of the well by required capacity pump including drawdown and recovery
test etc. complete
Considering 72 hrs.
(a) Hire charge of pump in/c
spare and maintenance 72 hrs @ 156.25 Per hour = 11250
(b) Fuel for pump:
@ 3.75 liter per hour 270 liter @ 65 Per liter = 17550
(c) Foreman: @ 1 No. per 8 hrs 9 Nos. @ 350 each = 3150
(d) Skilled labour 6 Nos. @ 200 each = 1200
(e) Local carriage, T & P L.S. = 487.5
Total = 33637.5
Profit 0.1 = 3363.75
Overhead 0.035 = 1177.31
= 38178.56
Add VAT with adjustment factor 1.04712 0.045 = 1798.99
Grand total = 39977.55
Rate per hour = 555.24
Say, 555 .00 Per Hr.