Item 27.32
Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ 350 each = 350
(b) Skilled labour 6 Nos. @ 200 each = 1200
(c) Local carriage, T & P L.S. = 150
Total = 1700
Profit 0.1 = 170
Overhead 0.035 = 59.5
= 1929.5
Add VAT with adjustment factor 1.04712 0.045 = 90.92
Grand total = 2020.42
Rate per rm. = 20.2
Say, 20 .00 Per rm.