Item 27.35.3
Supplying 150 mm dia uPVC strainer
Considering 1 meter
(a) 150 mm dia C-grade uPVC pipe 1 meter @ 750 Per meter = 750
(b) Making slot and cleaning 1 meter @ 22.5 Per meter = 22.5
(c) Carriage of materials L.S. = 12
Total = 784.5
Profit 0.1 = 78.45
Overhead 0.035 = 27.46
= 890.41
Add VAT with adjustment factor 1.04712 0.045 = 41.96
Grand total = 932.37
Rate per rm. = 932.37
Say, 932 .00 Per rm.