Item 27.40
Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ 350 each = 350
(b) Skilled labour 9 No. @ 200 each = 1800
(c) Local carriage, T & P L.S. = 187.5
Total = 2337.5
Profit 0.1 = 233.75
Overhead 0.035 = 81.81
= 2653.06
Add VAT with adjustment factor 1.04712 0.045 = 125.01
Grand total = 2778.07
Rate per rm. = 27.78
Say, 28 .00 each