Item 27.46
Long term pumping test of the well by required capacity pump including drawdown and
recovery test etc. complete
Considering 72 hrs.
(a) Hire charge of pump in/c
spare and maintenance 72 hrs @ 195.31 Per hour = 14062.32
(b) Fuel for pump:
@ 4.375 liter per hour 315 liter @ 65 Per liter = 20475
(c) Foreman: @ 1 No. per 8 hrs 9 Nos. @ 350 each = 3150
(d) Skilled labour 6 Nos. @ 200 each = 1200
(e) Local carriage, T & P L.S. = 525
Total = 39412.32
Profit 0.1 = 3941.23
Overhead 0.035 = 1379.43
= 44732.98
Add VAT with adjustment factor 1.04712 0.045 = 2107.84
Grand total = 46840.82
Rate per hour = 650.57
Say, 651 .00 Per Hr.