Item 27.5.2
(1) Cost for furnishing design of tube-well considering 2 bore = 9333.33
(2) Testing of water collected from 2 test bore = 8400
(3) Sieve analysis for sand
from different layers 6 tests @ 900 Per test = 5400
(3) Maintaining the bore holes and tools and plants etc. at site untill
satisfactory results are obtained from laboratory, filling and sealing
the bore holes 2 No. @ 2000 Per test bore = 4000
27133.33
Profit 0.1 = 2713.33
Overhead 0.035 = 949.67
= 30796.33
Add VAT with adjustment factor 1.04712 0.045 = 1451.14
Grand total = 32247.47
Say, 32247 .00 each