Item 27.62
Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ 350 each = 350
(b) Skilled labour 4 Nos. @ 200 each = 800
(c) Local carriage, T & P L.S. = 187.5
Total = 1337.5
Profit 0.1 = 133.75
Overhead 0.035 = 46.81
= 1518.06
Add VAT with adjustment factor 1.04712 0.045 = 71.53
Grand total = 1589.59
Rate per rm. = 15.9
Say, 16 .00 Per rm.
Card image cap
Card title

This is a wider card with supporting text below as a natural lead-in to additional content. This content is a little bit longer.

Last updated 3 mins ago