Item 27.69
Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ 350 each = 350
(b) Skilled labour 5 Nos. @ 200 each = 1000
(c) Local carriage, T & P L.S. = 187.5
Total = 1537.5
Profit 0.1 = 153.75
Overhead 0.035 = 53.81
= 1745.06
Add VAT with adjustment factor 1.04712 0.045 = 82.23
Grand total = 1827.29
Rate per rm. = 18.27
Say, 18 .00 Per rm.