Item 27.76
Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ 350 each = 350
(b) Skilled labour 6 Nos. @ 200 each = 1200
(c) Local carriage, T & P L.S. = 187.5
Total = 1737.5
Profit 0.1 = 173.75
Overhead 0.035 = 60.81
= 1972.06
Add VAT with adjustment factor 1.04712 0.045 = 92.92
Grand total = 2064.98
Rate per rm. = 20.65
Say, 21 .00 Per rm.