Item 27.8
Preparation and making gravel pack around the tube well fixtures (Shrouding the annular space
between the tube-well fixtures with pea-gravels)
Considering 2.8 cum
(a) Cost of pea-gravels including
20% for caving and siltation 3.36 cum. @ 1412.6 each = 4746.34
(b) Labour for screening out the larger
and smaller size of peagravels 1 No. @ 150 each = 150
(c) Labour for packing of peagravels with care:
Skilled labour 1 No. @ 200 Per liter = 200
(d) Local carriage, T & P L.S. = 75
Total = 5171.34
Profit 0.1 = 517.13
Overhead 0.035 = 181
= 5869.47
Add VAT with adjustment factor 1.04712 0.045 = 276.57
Grand total = 6146.04
Rate per cum. = 2195.01
Say, 2195 .00 Per cum.