Item 27.80
Construction of Platform
Considering 1.40 m x 1.00 m size platform and 1 m long drain
1. Cost for making platform
(a) Earth cutting 0.67 cum @ 49.88 Per cum = 33.42
(b) Sand filling 0.26 cum @ 400.38 Per cum = 104.1
(c) Brick work (1:6) 0.29 cum. @ 3059.78 Per cum = 887.34
(d) C.C. (1:2:4) 0.24 cum @ 4649.28 Per cum = 1115.83
(e) 12 mm plaster (1:4) in/c n.c.f. 2 sqm. @ 146.18 Per sqm. = 292.36
2. Cost for making drain
(a) Earth cutting 0.06 cum @ 49.88 Per cum = 2.99
(b) Brick work (1:6) 0.06 cum @ 3059.78 Per cum = 183.59
(c) 12 mm plaster (1:4) in/c n.c.f. 0.7 sqm @ 146.18 Per sqm. = 102.33
Total = 2721.96
Profit 0.1 = 272.2
Overhead 0.035 = 95.27
= 3089.43
Add VAT with adjustment factor 1.04712 0.045 = 145.58
Grand total = 3235.01
Rate each. = 3235.01
Say, 3235 .00 each.