Item 28.1.2
Installation of 50 PSI API 5L, Grade-B ERW M.S. Pipe line for supplying
Titas Gas. 50 mm ND (60.30 mm O.D) M.S. pipe.
Considering 100 rft. of pipe line
(a) Materials:
(i) Cost of pipe 100 rft. @ 174 Per rft = 17400
(ii) Cost of tape: 2" x 200'-0" 3 Roll @ 596 Per roll = 1788
(iii) Cost of primer 0.757 liter @ 228 Per liter = 172.6
(b) Labour:
(i) Cutting trenches:
100'-0" x 1'-6" x 3'-0"= 450 cft. @ 1412.5 Per % 0 cft. = 635.63
(ii) Laying and back-filling in/c levelling the top
surface with excavated earth 100 rft. @ 6.98 Per rft. = 698
(iii) Skilled labour for applying primer, wrapping the
pipe with tap in/c scrapping 100 rft. @ 5 Per rft. = 500
(iv) Carrying from Titas Gas store to work side in/c loading & unloading L.S. = 225
Total = 21419.23
Incidental charges 0.1 = 2141.92
Profit 0.1 = 2141.92
Overhead 0.035 = 74.97
= 25778.04
Add VAT with adjustment factor 1.04712 0.045 = 1214.67
Grand total = 26992.71
Rate per rft. = 269.93
Rate per rm = 885.64
Say, 886 .00 Per rm.