Item 28.1.3
Installation of 50 PSI API 5L, Grade-B ERW M.S. Pipe line for supplying
Titas Gas 25 mm ND (33.40 mm O.D) M.S. pipe.
Considering 100 rft. of pipe line
(a) Materials:
(i) Cost of pipe 100 rft. @ 81 Per rft = 8100
(ii) Cost of tape: 2" x 200'-0" 1.5 Roll @ 596 Per roll = 894
(iii) Cost of primer 0.65 liter @ 228 Per liter = 148.2
(b) Labour:
(i) Cutting trenches:
100'-0" x 1'-6" x 3'-0"= 450 cft. @ 1412.5 Per % 0 cft. = 635.63
(ii) Laying and back-filling in/c levelling the top
surface with excavated earth 100 rft. @ 6.98 Per rft. = 698
(iii) Skilled labour for applying primer, wrapping the
pipe with tap in/c scrapping 100 rft. @ 5 Per rft. = 500
(iv) Carrying from Titas Gas store to work side in/c loading & unloading L.S. = 225
Total = 11200.83
Incidental charges 0.1 = 1120.08
Profit 0.1 = 1120.08
Overhead 0.035 = 39.2
= 13480.19
Add VAT with adjustment factor 1.04712 0.045 = 635.19
Grand total = 14115.38
Rate per rft. = 141.15
Rate per rm = 463.11
Say, 463 .00 Per rm.