Item 28.2
Sand filling the trench with sand of F.M. 0.8
Considering: 100'-0" x 1'-6" x 1'-0"= 150 cft.
(a) Sand in/c 30% for compaction 195 cft. @ 750 Per % cft. = 1462.5
(b) Labour for watering, levelling
& compaction etc. 1 No. @ 150 each = 150
(c) Local carriage & sundries L.S. = 90
Total = 1702.5
Incidental charges 0.1 = 170.25
Profit 0.1 = 170.25
Overhead 0.035 = 5.96
= 2048.96
Add VAT with adjustment factor 1.04712 0.045 = 96.55
Grand total = 2145.51
Rate per cft.. = 14.3
Rate per cum = 505
Say, 505 .00 Per cum.