Item 28.7
Construction of 5'-0" x 5'-0" x 5'-0" size O.D. standard size valve pit in/c providing standard M.S.
sheet cover as per drawing approved by Titas Gas T&D Co. Ltd. (3'-4" x 3'-4" x 4'-4.5" inside clear)
Considering 1 No.
(a) Materials:
(i) Valve pit as per Titas Gas
T&D Co. Ltd. design 1 No. @ 16166.7 each = 16166.7
(ii) M.S. sheet cover supplied by Titas
Gas T&D Co. Ltd. 1 No. @ 11110 each = 11110
(b) Masonry pit
(i) Earth cutting 405 cft. @ 1412.5 Per % 0 cft. = 572.06
(ii) Brick flat soling 33.99 sft. @ 1830 Per % sft. = 622.02
(iii) Plain concrete (1:3:6) 33.99 sft. @ 2022.78 Per % sft. = 687.54
(iv) Brick-work (1:6) 62.26 cft. @ 8664.25 Per % cft. = 5394.36
(v) Plaster with n.c.f. 163.83 sft. @ 1358 Per % sft. = 2224.81
(vi) 38 mm patent stone flooring (1:2:4) 11.09 sft. @ 1548.62 Per % sft. = 171.74
(vii) Sand filling (F.M. 0.8) 275.51 cft. @ 1133.75 Per % cft. = 3123.59
(viii) Fitting-fixing & carrying of pit-cover L.S. = 2250
(c) Labour for loading-unloading L.S. = 150
Total = 42472.82
Incidental charges 0.1 = 4247.28
Profit 0.1 = 4247.28
Overhead 0.035 = 148.65
= 51116.03
Add VAT with adjustment factor 1.04712 0.045 = 2408.61
Grand total = 53524.64
Say, 53525 .00 each