Item 29.4
Termite treatment in existing structures by making downwardly slanted holes at a depth of 9"
from the existing finished F.L./G.L. inside and outside the building and applying the
emulsion of anti-termite chemicals DURSBAN 20EC to be mixed with water
at 1:19 ratio into the holes @ 25 ml per hole in/c mending good the damages.
Considering 100 holes
(a) DURS BAN 20EC 1.25 liter @ 567 Per liter = 708.75
(b) Labour for cutting holes 100 holes @ 7.5 Per hole = 750
(c) C.C. (1:2:4):
100 x 1/2 x 1/2 x 9"= 1.56 cft. @ 131.65 Per cft. = 205.37
(d) Labour for preparing & applying
(i) Skilled labour 2 Nos. @ 200 each = 400
(ii) Skilled technician 0.25 No. @ 400 each = 100
(e) T & P, sundries, drilling machine & sprayer L.S. = 34.4
(f) Local carriage L.S. = 48
Total = 2246.52
Profit 0.1 = 224.65
Overhead 0.035 = 78.63
= 2549.8
Add VAT with adjustment factor 1.04712 0.045 = 120.15
Grand total = 2669.95
Rate per hole. = 26.7
Say, 27 .00 Per hole.