Item 29.9
Destruction of termite nests
Considering 1 No. nest.
(a) Earth-work in excavation
1 x 1 m x 1.5 m x 1.5 m = 2.25 cum. @ 49.88 Per cum. = 112.23
(b) Cost of DURSBAN 20EC 1.1 liter @ 567 Per liter = 623.7
(c) Skilled Technician 0.25 No. @ 400 each = 100
(d) Skilled labour 0.5 No. @ 200 each = 100
Total = 935.93
Profit 0.1 = 93.59
Overhead 0.035 = 32.76
= 1062.28
Add VAT with adjustment factor 1.04712 0.045 = 50.06
Grand total = 1112.34
Rate each.. = 1112.34
Say, 1112 .00 each.