Item 30.14.2
Supplying and placing 60 mm colored Uni-block for Walk Way on 50 mm stabilized sand base:
compressive strength 15N/mm2
Consideration of 100 sft of work
(a) Material
(i) 60 mm colored uni-block
(222 x 110 x 60 mm) 388 Nos. @ 11.5 Per block = 4462
(ii) Sand 30 cft. @ 1300 Per % cft. = 390
(iii) Transportation of block 388 Nos. @ 1.1 each = 426.8
(b) Labour
(i) Head mason 0.1 No. @ 350 each = 35
(ii) Mason 1 No. @ 250 each = 250
(iii) Ordinary Labour 2 Nos. @ 150 each = 300
(c) Tools & machinery 100 sft. @ 1.5 Per sft. = 150
(d) Local carriage, storage & sundries etc. LS. = 45
Total = 6058.8
Profit 0.1 = 605.88
Overhead 0.035 = 212.06
= 6876.74
Add VAT with adjustment factor 1.04712 0.045 = 324.03
Grand total = 7200.77
Rate per sft. = 72.01
Rate per sqm. = 775.12
Say, 775 .00 Per sqm.