Item 30.15.1
Supplying and placing 60 mm grey Uni-block for major walk-way, car porch on 50 mm stabilized
sand base: compressive strength 49 N/mm2
Consideration of 100 sft. of work.
(a) Material
9i) 60 mm grey uni-block
(222 x 110 x 60 mm) 388 Nos. @ 12.5 Per block = 4850
(ii) Sand 30 cft. @ 1300 Per % cft. = 390
(iii) Transportation of block 388 Nos. @ 1.1 each = 426.8
(b) Labour
(i) Head mason 0.1 No. @ 350 each = 35
(ii) Mason 1 No. @ 250 each = 250
(iii) Ordinary Labour 2 Nos. @ 150 each = 300
(c) Tools & machinery 100 sft. @ 1.5 Per sft. = 150
(d0 Local carriage, storage & sundries etc. LS. = 45
Total = 6446.8
Profit 0.1 = 644.68
Overhead 0.035 = 225.64
= 7317.12
Add VAT with adjustment factor 1.04712 0.045 = 344.79
Grand total = 7661.91
Rate per sft. = 76.62
Rate per sqm. = 824.74