Item 30.17.1
Supplying and placing grey Rectangular-block on 50 mm stabilized sand base:
compressive strength 15N/mm2
Consideration of 100 sft. of work
(a) Material
(i) Grey rec-block
(200 x 100 x 60 mm) 474 Nos. @ 14 Per block = 6636
(ii) Sand 30 cft. @ 1300 Per % cft. = 390
(iii) Transportation of block 474 Nos. @ 1.1 each = 521.4
(b) Labour
(i) Head mason 0.1 No. @ 350 each = 35
(ii) Mason 0.75 No. @ 250 each = 187.5
(iii) Ordinary Labour 2 Nos. @ 150 each = 300
(c) Local carriage, storage & sundries etc. LS. = 45
Total = 8114.9
Profit 0.1 = 811.49
Overhead 0.035 = 284.02
= 9210.41
Add VAT with adjustment factor 1.04712 0.045 = 434
Grand total = 9644.41
Rate per sft. = 96.44
Rate per sqm. = 1038.08
Say, 1038 .00 Per sqm.