Item 30.17.2
Supplying and placing colored Rec-block on 50 mm stabilized sand base:
compressive strength 15N/mm2
Consideration of 100 sft. work
(a) Material
(i) Colored rec-block
(200 x 100 x 60 mm) 474 Nos. @ 17 Per block = 8058
(ii) Sand 30 cft. @ 1300 Per % cft. = 390
(iii) Transportation of block 474 Nos. @ 1.1 each = 521.4
(b) Labour
(i) Head mason 0.1 No. @ 350 each = 35
(ii) Mason 0.75 No. @ 250 each = 187.5
(iii) Ordinary Labour 2 Nos. @ 150 each = 300
(c) Local carriage, storage & sundries etc. LS. = 45
Total = 9536.9
Profit 0.1 = 953.69
Overhead 0.035 = 333.79
= 10824.38
Add VAT with adjustment factor 1.04712 0.045 = 510.05
Grand total = 11334.43
Rate per sft. = 113.34
Rate per sqm. = 1219.99
Say, 1220 .00 Per sqm.