Item 30.21.1
Providing 418 x 330 x 17 mm red/brown color roof tiles on prefabricated truss
Consideration of 100 Nos.
(a) Materials
(i) Red/brown color concrete
roof tiles in/c wastage 102 Nos. @ 37 each = 3774
(ii) J-hook with nut & washer 60 Nos. @ 7 each = 420
(iii) Transportation 102 Nos. @ 2 each = 204
(b) Labour
(i) Lifting & placing on shutter 102 Nos. @ 1.5 Per sft. = 153
(c) Tools and machinery for 102 Nos. @ 2.25 Per sft. 229.5
Total = 4780.5
Profit 0.1 = 478.05
Overhead 0.035 = 167.32
= 5425.87
Add VAT with adjustment factor 1.04712 0.045 = 255.67
Grand total = 5681.54
Rate each. = 56.82
Say, 57 .00 each.