Item 30.21.2
Providing 418 x 330 x 17 mm Oriental red/Ruset gold/Mehagany color roof tiles on prefabricated truss
Consideration of 100 Nos.
(a) Materials
(i) Oriental red/Ruset/Mehagany color concrete
roof tiles in/c wastage 102 Nos. @ 33 each = 3366
(ii) J-hook with nut & washer 60 Nos. @ 7 each = 420
(iii) Transportation 102 Nos. @ 2 each = 204
(b) Labour
(i) Lifting & placing on shutter 102 Nos. @ 1.5 Per sft. = 153
(c) Tools and machinery for 102 Nos. @ 2.25 Per sft. 229.5
Total = 4372.5
Profit 0.1 = 437.25
Overhead 0.035 = 153.04
= 4962.79
Add VAT with adjustment factor 1.04712 0.045 = 233.85
Grand total = 5196.64
Rate each. = 51.97
Say, 52 .00 each.