Item 30.21.4
Providing 418 x 330 x 17 mm green color roof tiles on prefabricated truss
Consideration of 100 Nos.
(a) Materials
(i) Green red color concrete
roof tiles in/c wastag 102 Nos. @ 40 each = 4080
(ii) J-hook with nut & washer 60 Nos. @ 7 each = 420
(iii) Transportation 102 Nos. @ 2 each = 204
(b) Labour
(i) Lifting & placing on shutter 100 Nos. @ 1.5 Per sft. = 150
(c) Tools and machinery for 100 Nos. @ 1.5 Per sft. 150
Total = 5004
Profit 0.1 = 500.4
Overhead 0.035 = 175.14
= 5679.54
Add VAT with adjustment factor 1.04712 0.045 = 267.62
Grand total = 5947.16
Rate each. = 59.47
Say, 59 .00 each.