Item 30.22
Supplying and placing of concrete kerb stone (K3) as per direction of the engineer in charge
Consideration of 100 Nos.
(a) Materials
(i) Kerb-stone (600 x 300 x 100/60 mm) 100 Nos. @ 105 each = 10500
(ii) Cement for pointing & jointing 1.5 bags @ 370 Per bag = 555
(iii) Transportation 100 Nos. @ 20 each = 2000
(b) Labour
(i) Local carriage & placing 100 Nos. @ 4.5 each = 450
Total = 13505
Profit 0.1 = 1350.5
Overhead 0.035 = 472.68
= 15328.18
Add VAT with adjustment factor 1.04712 0.045 = 722.27
Grand total = 16050.45
Rate each. = 160.5
Say, 161 .00 each.