Item 31.4.2
Considering next 9 meter boring in 0.4 x 1.1 = 0.44 day in/c depth for SPT operation
(a) Hire charge of boring rig 0.44 day @ 2100 Per day = 924
(b) Wages for man power
(i) Foreman
(1 x 50% per day x 0.44 day) 0.22 manday @ 350 each = 77
(ii) Rig operators
(1 x 50% per day x 0.44 day) 0.22 manday @ 300 each = 66
(iii) Helper to rig operators
(6 x 50% per day x 0.44 day) 1.32 mandays @ 250 each = 330
Total = 1397
Profit 0.1 = 139.7
Overhead 0.035 = 48.9
= 1585.6
Add VAT with adjustment factor 1.04712 0.045 = 74.71
Grand total = 1660.31
Rate per meter = 184.48
Say, 184 .00 Per meter