Item 31.4.3
Considering next 9 meter boring in 0.44 x 1.1= 0.48 day in/c depth for SPT operation
(a) Hire charge of boring rig 0.48 days @ 2100 Per day = 1008
(b) Wages for man power
(i) Foreman
(1 x 50% per day x 0.48 days) 0.24 manday @ 350 each = 84
(ii) Rig operators
(1 x 50% per day x 0.48 days) 0.24 manday @ 300 each = 72
(iii) Helper to rig operators
(6 x 50% per day x 0.48 days) 1.44 manday @ 250 each = 360
Total = 1524
Profit 0.1 = 152.4
Overhead 0.035 = 53.34
= 1729.74
Add VAT with adjustment factor 1.04712 0.045 = 81.51
Grand total = 1811.25
Rate per meter = 201.25
Say, 201 .00 Per meter