Item 31.4.4
Considering next 9 meter boring in 0.48 x 1.1= 0.53 day in/c depth for SPT operation
(a) Hire charge of boring rig 0.53 day @ 2100 Per day = 1113
(b) Wages for man power
(i) Foreman (1 x 50% per day x 0.53 day) 0.27 manday @ 350 each = 94.5
(ii) Rig operators
(1 x 50% per day x 0.53 day) 0.27 manday @ 300 each = 81
(iii) Helper to rig operators
(6 x 50% per day x 0.53 day) 1.59 mandays @ 250 each = 397.5
Total = 1686
Profit 0.1 = 168.6
Overhead 0.035 = 59.01
= 1913.61
Add VAT with adjustment factor 1.04712 0.045 = 90.17
Grand total = 2003.78
Rate per meter = 222.64
Say, 223 .00 Per meter