Add VAT with adjustment factor (a) Ground floor | Overhead 1.06383 | 3.50% | = | Tk. | 762.21 |
Total 6.00% | = = | Tk. Tk. | 24,717.46 1,577.71 | ||
Grand Total Rate per cft Rate per cum | = = = | Tk. | 26,295.17 262.95 9,286.08 | ||
Say, Tk. | 9,286 | .00 per cum |
|
|
|
|
|
|
|
|
|
Item No.- 04.8 |
|
|
|
|
|
Brick work with 9.5" x 4.5" x 2.75" size 10 hole machine made rock-face/textured klinker facing bricks (1:4) |
|
|
|
|
|
Considering 100 cft work
| 13,500.00 | per % 0 nos | = | Tk. | 14,850.00 |
| 1,400.00 | per % cft | = | Tk. | 560.00 |
| 395.00 | per bag | = | Tk. | 2,567.50 |
| 600.00 | per day | = | Tk. | 150.00 |
| 500.00 | per day | = | Tk. | 1,000.00 |
| 390.00 | per day | = | Tk. | 585.00 |
| 320.00 | per day | = | Tk. | 640.00 |
cleaning bricks 1 no @ Tk. | 320.00 | per day | = | Tk. | 320.00 |
| 320.00 | per day | = | Tk. | 160.00 |
@ 1/8 labour per day: 0.875 nos @ Tk. | 320.00 | per day | = | Tk. | 280.00 |
| 9.00 | per sft | = | Tk. | 225.00 |
| LS |
| = | Tk. | 160.00 |
|
| Sub - Total | = | Tk. | 21,497.50 |
| Profit | 10.00% | = | Tk. | 2,149.75 |
| Overhead | 3.50% | = | Tk. | 752.41 |
|
| Total | = | Tk. | 24,399.66 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 1,557.43 |
|
| Grand Total | = | Tk. | 25,957.09 |
(a) Ground floor |
| Rate per cft | = | Tk. | 259.57 |
|
| Rate per cum | = | Tk. | 9,166.71 |
Say, Tk. | 9,167 | .00 per cum |
|
|
|
|
|
|
|
|
|
Item No.- 04.9 |
|
|
|
|
|
Brick work with 9.5" x 4.5" x 2.75" size 3 hole machine made reinforced klinker facing bricks (1:4) |
|
|
|
|
|
Considering 100 cft work
| 21,500.00 | per % 0 nos | = | Tk. | 23,650.00 |
Sand (F.M 2.2) in/c wastage 24 cft @ Tk. | 4,500.00 | per % cft | = | Tk. | 1,080.00 |
| 1,400.00 | per % cft | = | Tk. | 560.00 |
| 395.00 | per bag | = | Tk. | 2,567.50 |
| 600.00 | per day | = | Tk. | 150.00 |
| 500.00 | per day | = | Tk. | 1,000.00 |
| 390.00 | per day | = | Tk. | 585.00 |
| 320.00 | per day | = | Tk. | 640.00 |
& cleaning bricks 1 no @ Tk. | 320.00 | per day | = | Tk. | 320.00 |
| 320.00 | per day | = | Tk. | 160.00 |
@ 1/8 labour per day: 0.875 no @ Tk. | 320.00 | per day | = | Tk. | 280.00 |
| 9.00 | per sft | = | Tk. | 225.00 |
|
| LS | = | Tk. | 160.00 |
|
| Sub - Total | = | Tk. | 31,377.50 |
| Profit | 10.00% | = | Tk. | 3,137.75 |
| Overhead | 3.50% | = | Tk. | 1,098.21 |
|
| Total | = | Tk. | 35,613.46 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 2,273.20 |