Prev Next
īģŋ

Item No.- 04.27

 

 

 

 

 

 

 

 

 

38 mm thick artificial patent stone flooring (1:2:4) with brick chips Considering 100 cft of work covering 800 sft area

 

 

 

 

 

 

 

 

1.

Bricks @ 8.5 nos per cft chips

765

nos

@

Tk.

8,700.00

per % 0 nos

=

Tk.

6,655.50

2.

Sand (F.M. 1.2)

22.5

cft

@

Tk.

1,400.00

per % cft

=

Tk.

315.00

3.

Sand (F.M. 2.2)

22.5

cft

@

Tk.

4,500.00

per % cft

=

Tk.

1,012.50

4.

Cement

18

bags

@

Tk.

395.00

per bag

=

Tk.

7,110.00

5.

Breaking brick chips

 

 

 

 

 

 

 

 

 

 

in/c screening

90

cft

@

Tk.

1,200.00

per % cft

=

Tk.

1,080.00

6.

Labour for 7 days curing

 

 

 

 

 

 

 

 

 

 

@ 1/8 labour per day.

0.875

no

@

Tk.

320.00

per day

=

Tk.

280.00

7.

Local carriage, sundries, T & P and washing of sand etc.

 

 

 

 

LS

=

Tk.

480.00

 

 

 

 

 

 

 

Sub-total

=

Tk.

16,933.00

 

 

 

 

 

 

For 100 sft of work

=

Tk.

2,116.63

8.

Extra cement for finishing

1/2

bag

@

Tk.

395.00

per bag

=

Tk.

197.50

9.

Labour cost:

 

 

 

 

 

 

 

 

 

  1.  

Head mason

1/5

no

@

Tk.

600.00

per day

=

Tk.

120.00

  1.  

Mason

3/4

no

@

Tk.

500.00

per day

=

Tk.

375.00

  1.  

Skilled labour

1

no

@

Tk.

390.00

per day

=

Tk.

390.00

  1.  

Ordinary labour

1

no

@

Tk.

320.00

per day

=

Tk.

320.00

10.

Extra cost of Garjan batten for side shutter

 

 

 

 

 

 

 

 

 

 

2 x 4 x 5'-0" x 1.5" x 3/4" =

0.31

cft

 

 

 

 

 

 

 

 

Add 5% wastage

0.02

cft

 

 

 

 

 

 

 

 

 

0.33

cft

@

Tk.

2,000.00

per cft

 

 

 

 

 

Using 10 times

@

Tk.

200.00

per cft

=

Tk.

66.00

11.

Labour for shuttering

 

 

 

 

 

 

 

 

 

 

2 x 4 x 5'-0" x 1.5" =

5

sft

@

Tk.

2.50

per sft

=

Tk.

12.50

 

 

 

 

 

 

 

Sub - Total

=

Tk.

3,597.63

 

 

 

 

 

 

Profit

10.00%

=

Tk.

359.76

 

 

 

 

 

 

Overhead

3.50%

=

Tk.

125.92

 

 

 

 

 

 

 

Total

=

Tk.

4,083.31

 

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

260.64

 

 

 

 

 

 

 

Grand Total

=

Tk.

4,343.95

(i)

Ground floor

 

 

 

 

 

Rate per sft

=

Tk.

43.44

 

 

 

 

 

 

 

Rate per sqm

=

Tk.

467.59

 

 

 

 

Say,

Tk.

468

.00 per sqm

 

 

 

 

 

 

 

 

 

Item No.- 04.28

 

 

 

 

 

 

 

 

 

25 mm thick artificial patent stone flooring (1:2:4) with 1/2" down graded stone chips

 

 

 

 

 

 

Considering 100 cft of work covering 1200 sft area

 

 

 

 

 

 

  1.  

Crushed stone chips

90

cft

@

Tk.

16,500.00

per % cft

=

Tk.

14,850.00

  1.  

Sand (F.M. 1.2)

22.5

cft

@

Tk.

1,400.00

per % cft

=

Tk.

315.00

  1.  

Sand (F.M. 2.2)

22.5

cft

@

Tk.

4,500.00

per % cft

=

Tk.

1,012.50

  1.  

Cement

18

bags

@

Tk.

395.00

per bag

=

Tk.

7,110.00

  1.  

Labour for 7 days curing

 

 

 

 

 

 

 

 

 

 

@ 1/8 labour per day.

0.875

no

@

Tk.

320.00

per day

=

Tk.

280.00

  1.  

Local carriage, sundries, T & P and washing of sand etc.

 

 

 

 

LS

=

Tk.

480.00

 

 

 

 

 

 

 

Sub-total

=

Tk.

24,047.50

 

 

 

 

 

 

For 100 sft of work

=

Tk.

2,003.96

  1.  

Extra cement for finishing

1/2

bag

@

Tk.

395.00

per bag

=

Tk.

197.50

  1.  

Labour cost:

 

 

 

 

 

 

 

 

 

  1.  

Head mason

1/5

no

@

Tk.

600.00

per day

=

Tk.

120.00

  1.  

Mason

3/4

no

@

Tk.

500.00

per day

=

Tk.

375.00

  1.  

Skilled labour

1

no

@

Tk.

390.00

per day

=

Tk.

390.00

  1.  

Ordinary labour

1

no

@

Tk.

320.00

per day

=

Tk.

320.00

10.

Extra cost of Garjan batten for side shutter

 

 

 

 

 

 

 

 

 

 

2 x 4 x 5'-0" x 1" x 3/4" =

0.21

cft

 

 

 

 

 

 

 

 

Add 5% wastage

0.01

cft

 

 

 

 

 

 

 

 

 

0.22

cft

@

Tk.

2,000.00

per cft