Item No.- 04.27 |
|
|
|
|
|
|
|
|
| |
38 mm thick artificial patent stone flooring (1:2:4) with brick chips Considering 100 cft of work covering 800 sft area |
|
|
|
|
|
|
|
| ||
1. | Bricks @ 8.5 nos per cft chips | 765 | nos | @ | Tk. | 8,700.00 | per % 0 nos | = | Tk. | 6,655.50 |
2. | Sand (F.M. 1.2) | 22.5 | cft | @ | Tk. | 1,400.00 | per % cft | = | Tk. | 315.00 |
3. | Sand (F.M. 2.2) | 22.5 | cft | @ | Tk. | 4,500.00 | per % cft | = | Tk. | 1,012.50 |
4. | Cement | 18 | bags | @ | Tk. | 395.00 | per bag | = | Tk. | 7,110.00 |
5. | Breaking brick chips |
|
|
|
|
|
|
|
|
|
| in/c screening | 90 | cft | @ | Tk. | 1,200.00 | per % cft | = | Tk. | 1,080.00 |
6. | Labour for 7 days curing |
|
|
|
|
|
|
|
|
|
| @ 1/8 labour per day. | 0.875 | no | @ | Tk. | 320.00 | per day | = | Tk. | 280.00 |
7. | Local carriage, sundries, T & P and washing of sand etc. |
|
|
|
| LS | = | Tk. | 480.00 | |
|
|
|
|
|
|
| Sub-total | = | Tk. | 16,933.00 |
|
|
|
|
|
| For 100 sft of work | = | Tk. | 2,116.63 | |
8. | Extra cement for finishing | 1/2 | bag | @ | Tk. | 395.00 | per bag | = | Tk. | 197.50 |
9. | Labour cost: |
|
|
|
|
|
|
|
|
|
Head mason | 1/5 | no | @ | Tk. | 600.00 | per day | = | Tk. | 120.00 | |
Mason | 3/4 | no | @ | Tk. | 500.00 | per day | = | Tk. | 375.00 | |
Skilled labour | 1 | no | @ | Tk. | 390.00 | per day | = | Tk. | 390.00 | |
Ordinary labour | 1 | no | @ | Tk. | 320.00 | per day | = | Tk. | 320.00 | |
10. | Extra cost of Garjan batten for side shutter |
|
|
|
|
|
|
|
|
|
| 2 x 4 x 5'-0" x 1.5" x 3/4" = | 0.31 | cft |
|
|
|
|
|
|
|
| Add 5% wastage | 0.02 | cft |
|
|
|
|
|
|
|
|
| 0.33 | cft | @ | Tk. | 2,000.00 | per cft |
|
|
|
|
| Using 10 times | @ | Tk. | 200.00 | per cft | = | Tk. | 66.00 | |
11. | Labour for shuttering |
|
|
|
|
|
|
|
|
|
| 2 x 4 x 5'-0" x 1.5" = | 5 | sft | @ | Tk. | 2.50 | per sft | = | Tk. | 12.50 |
|
|
|
|
|
|
| Sub - Total | = | Tk. | 3,597.63 |
|
|
|
|
|
| Profit | 10.00% | = | Tk. | 359.76 |
|
|
|
|
|
| Overhead | 3.50% | = | Tk. | 125.92 |
|
|
|
|
|
|
| Total | = | Tk. | 4,083.31 |
|
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 260.64 | ||
|
|
|
|
|
|
| Grand Total | = | Tk. | 4,343.95 |
(i) | Ground floor |
|
|
|
|
| Rate per sft | = | Tk. | 43.44 |
|
|
|
|
|
|
| Rate per sqm | = | Tk. | 467.59 |
|
|
|
| Say, | Tk. | 468 | .00 per sqm |
|
|
|
|
|
|
|
|
| |||||
Item No.- 04.28 |
|
|
|
|
|
|
|
|
| |
25 mm thick artificial patent stone flooring (1:2:4) with 1/2" down graded stone chips |
|
|
|
|
|
| ||||
Considering 100 cft of work covering 1200 sft area |
|
|
|
|
|
| ||||
Crushed stone chips | 90 | cft | @ | Tk. | 16,500.00 | per % cft | = | Tk. | 14,850.00 | |
Sand (F.M. 1.2) | 22.5 | cft | @ | Tk. | 1,400.00 | per % cft | = | Tk. | 315.00 | |
Sand (F.M. 2.2) | 22.5 | cft | @ | Tk. | 4,500.00 | per % cft | = | Tk. | 1,012.50 | |
Cement | 18 | bags | @ | Tk. | 395.00 | per bag | = | Tk. | 7,110.00 | |
Labour for 7 days curing |
|
|
|
|
|
|
|
|
| |
| @ 1/8 labour per day. | 0.875 | no | @ | Tk. | 320.00 | per day | = | Tk. | 280.00 |
Local carriage, sundries, T & P and washing of sand etc. |
|
|
|
| LS | = | Tk. | 480.00 | ||
|
|
|
|
|
|
| Sub-total | = | Tk. | 24,047.50 |
|
|
|
|
|
| For 100 sft of work | = | Tk. | 2,003.96 | |
Extra cement for finishing | 1/2 | bag | @ | Tk. | 395.00 | per bag | = | Tk. | 197.50 | |
Labour cost: |
|
|
|
|
|
|
|
|
| |
Head mason | 1/5 | no | @ | Tk. | 600.00 | per day | = | Tk. | 120.00 | |
Mason | 3/4 | no | @ | Tk. | 500.00 | per day | = | Tk. | 375.00 | |
Skilled labour | 1 | no | @ | Tk. | 390.00 | per day | = | Tk. | 390.00 | |
Ordinary labour | 1 | no | @ | Tk. | 320.00 | per day | = | Tk. | 320.00 | |
10. | Extra cost of Garjan batten for side shutter |
|
|
|
|
|
|
|
|
|
| 2 x 4 x 5'-0" x 1" x 3/4" = | 0.21 | cft |
|
|
|
|
|
|
|
| Add 5% wastage | 0.01 | cft |
|
|
|
|
|
|
|
|
| 0.22 | cft | @ | Tk. | 2,000.00 | per cft |
|
|
|