| For 100 sft of work | = | Tk. | 2,135.63 | |
Extra cement for finishing | 1/2 | bag | @ | Tk. | 395.00 | per bag | = | Tk. | 197.50 | |
Labour cost: |
|
|
|
|
|
|
|
|
| |
Head mason | 1/5 | no | @ | Tk. | 600.00 | per day | = | Tk. | 120.00 | |
Mason | 3/4 | no | @ | Tk. | 500.00 | per day | = | Tk. | 375.00 | |
Skilled labour | 1 | no | @ | Tk. | 390.00 | per day | = | Tk. | 390.00 | |
Ordinary labour | 1 | no | @ | Tk. | 320.00 | per day | = | Tk. | 320.00 | |
Extra cost of Garjan batten for side shutter |
|
|
|
|
|
|
|
|
| |
| 2 x 4 x 5'-0" x 1" x 3/4" = | 0.21 | cft |
|
|
|
|
|
|
|
| Add 5% wastage | 0.01 | cft |
|
|
|
|
|
|
|
|
| 0.22 | cft | @ | Tk. | 2,000.00 | per cft |
|
|
|
|
| Using 10 times | @ | Tk. | 200.00 | per cft | = | Tk. | 44.00 | |
Labour for shuttering |
|
|
|
|
|
|
|
|
| |
| 2 x 4 x 5'-0" x 1" = | 3.33 | sft | @ | Tk. | 2.50 | per sft | = | Tk. | 8.33 |
|
|
|
|
|
|
| Sub - Total | = | Tk. | 3,590.46 |
|
|
|
|
| Profit | 10.00% | = | Tk. | 359.05 | |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 125.67 | |
|
|
|
|
|
|
| Total | = | Tk. | 4,075.18 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 260.12 | |||
|
|
|
|
|
|
| Grand Total | = | Tk. | 4,335.30 |
(i) | Ground floor |
|
|
|
|
| Rate per sft | = | Tk. | 43.35 |
|
|
|
|
|
|
| Rate per sqm | = | Tk. | 466.62 |
|
|
|
| Say, | Tk. | 467 | .00 per sqm |
|
|
|
|
|
|
|
|
| |||||
Item No.- 04.31 |
|
|
|
|
| |||||
38 mm thick artificial patent stone flooring (1: 1.5 : 3) with 1/2" down graded stone chips |
|
|
|
|
| |||||
| Considering 100 cft of work covering 800 sft area |
|
|
|
|
|
|
|
|
|
Crushed stone chips | 90 | cft | @ | Tk. | 16,500.00 | per % cft | = | Tk. | 14,850.00 | |
Sand (F.M. 1.2) | 22.5 | cft | @ | Tk. | 1,400.00 | per % cft | = | Tk. | 315.00 | |
Sand (F.M. 2.2) | 22.5 | cft | @ | Tk. | 4,500.00 | per % cft | = | Tk. | 1,012.50 | |
Cement | 22 | bags | @ | Tk. | 395.00 | per bag | = | Tk. | 8,690.00 | |
Labour for 7 days curing |
|
|
|
|
|
|
|
|
| |
| @ 1/8 labour per day. | 0.875 | no | @ | Tk. | 320.00 | per day | = | Tk. | 280.00 |
Local carriage, sundries, T & P and washing of sand etc. |
|
|
|
| LS | = | Tk. | 480.00 | ||
|
|
|
|
|
|
| Sub-total | = | Tk. | 25,627.50 |
|
|
|
|
|
| For 100 sft of work | = | Tk. | 3,203.44 | |
Extra cement for finishing | 1/2 | bag | @ | Tk. | 395.00 | per bag | = | Tk. | 197.50 | |
Labour cost: |
|
|
|
|
|
|
|
|
| |
Head mason | 1/5 | no | @ | Tk. | 600.00 | per day | = | Tk. | 120.00 | |
Mason | 3/4 | no | @ | Tk. | 500.00 | per day | = | Tk. | 375.00 | |
Skilled labour | 1 | no | @ | Tk. | 390.00 | per day | = | Tk. | 390.00 | |
Ordinary labour | 1 | no | @ | Tk. | 320.00 | per day | = | Tk. | 320.00 | |
Extra cost of Garjan batten for side shutter |
|
|
|
|
|
|
|
|
| |
| 2 x 4 x 5'-0" x 1.5" x 3/4" = | 0.31 | cft |
|
|
|
|
|
|
|
| Add 5% wastage | 0.02 | cft |
|
|
|
|
|
|
|
|
| 0.33 | cft | @ | Tk. | 2,000.00 | per cft |
|
|
|
|
| Using 10 times | @ | Tk. | 200.00 | per cft | = | Tk. | 66.00 | |
Labour for shuttering |
|
|
|
|
|
|
|
|
| |
| 2 x 4 x 5'-0" x 1.5" = | 5 | sft | @ | Tk. | 2.50 | per sft | = | Tk. | 12.50 |
|
|
|
|
|
|
| Sub - Total | = | Tk. | 4,684.44 |
|
|
|
|
| Profit | 10.00% | = | Tk. | 468.44 | |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 163.96 | |
|
|
|
|
|
|
| Total | = | Tk. | 5,316.84 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 339.37 | |||
|
|
|
|
|
|
| Grand Total | = | Tk. | 5,656.21 |
(i) | Ground floor |
|
|
|
|
| Rate per sft | = | Tk. | 56.56 |
|
|
|
|
|
|
| Rate per sqm | = | Tk. | 608.81 |
|
|
|
| Say, | Tk. | 609 | .00 per sqm |
|
|
|