Prev Next
īģŋ

 

 

 

 

 

 

For 100 sft of work

=

Tk.

2,135.63

  1.  

Extra cement for finishing

1/2

bag

@

Tk.

395.00

per bag

=

Tk.

197.50

  1.  

Labour cost:

 

 

 

 

 

 

 

 

 

  1.  

Head mason

1/5

no

@

Tk.

600.00

per day

=

Tk.

120.00

  1.  

Mason

3/4

no

@

Tk.

500.00

per day

=

Tk.

375.00

  1.  

Skilled labour

1

no

@

Tk.

390.00

per day

=

Tk.

390.00

  1.  

Ordinary labour

1

no

@

Tk.

320.00

per day

=

Tk.

320.00

  1.  

Extra cost of Garjan batten for side shutter

 

 

 

 

 

 

 

 

 

 

2 x 4 x 5'-0" x 1" x 3/4" =

0.21

cft

 

 

 

 

 

 

 

 

Add 5% wastage

0.01

cft

 

 

 

 

 

 

 

 

 

0.22

cft

@

Tk.

2,000.00

per cft

 

 

 

 

 

Using 10 times

@

Tk.

200.00

per cft

=

Tk.

44.00

  1.  

Labour for shuttering

 

 

 

 

 

 

 

 

 

 

2 x 4 x 5'-0" x 1" =

3.33

sft

@

Tk.

2.50

per sft

=

Tk.

8.33

 

 

 

 

 

 

 

Sub - Total

=

Tk.

3,590.46

 

 

 

 

 

Profit

10.00%

=

Tk.

359.05

 

 

 

 

 

Overhead

3.50%

=

Tk.

125.67

 

 

 

 

 

 

 

Total

=

Tk.

4,075.18

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

260.12

 

 

 

 

 

 

 

Grand Total

=

Tk.

4,335.30

(i)

Ground floor

 

 

 

 

 

Rate per sft

=

Tk.

43.35

 

 

 

 

 

 

 

Rate per sqm

=

Tk.

466.62

 

 

 

 

Say,

Tk.

467

.00 per sqm

 

 

 

 

 

 

 

 

 

Item No.- 04.31

 

 

 

 

 

38 mm thick artificial patent stone flooring (1: 1.5 : 3) with 1/2" down graded stone chips

 

 

 

 

 

 

Considering 100 cft of work covering 800 sft area

 

 

 

 

 

 

 

 

 

  1.  

Crushed stone chips

90

cft

@

Tk.

16,500.00

per % cft

=

Tk.

14,850.00

  1.  

Sand (F.M. 1.2)

22.5

cft

@

Tk.

1,400.00

per % cft

=

Tk.

315.00

  1.  

Sand (F.M. 2.2)

22.5

cft

@

Tk.

4,500.00

per % cft

=

Tk.

1,012.50

  1.  

Cement

22

bags

@

Tk.

395.00

per bag

=

Tk.

8,690.00

  1.  

Labour for 7 days curing

 

 

 

 

 

 

 

 

 

 

@ 1/8 labour per day.

0.875

no

@

Tk.

320.00

per day

=

Tk.

280.00

  1.  

Local carriage, sundries, T & P and washing of sand etc.

 

 

 

 

LS

=

Tk.

480.00

 

 

 

 

 

 

 

Sub-total

=

Tk.

25,627.50

 

 

 

 

 

 

For 100 sft of work

=

Tk.

3,203.44

  1.  

Extra cement for finishing

1/2

bag

@

Tk.

395.00

per bag

=

Tk.

197.50

  1.  

Labour cost:

 

 

 

 

 

 

 

 

 

  1.  

Head mason

1/5

no

@

Tk.

600.00

per day

=

Tk.

120.00

  1.  

Mason

3/4

no

@

Tk.

500.00

per day

=

Tk.

375.00

  1.  

Skilled labour

1

no

@

Tk.

390.00

per day

=

Tk.

390.00

  1.  

Ordinary labour

1

no

@

Tk.

320.00

per day

=

Tk.

320.00

  1.  

Extra cost of Garjan batten for side shutter

 

 

 

 

 

 

 

 

 

 

2 x 4 x 5'-0" x 1.5" x 3/4" =

0.31

cft

 

 

 

 

 

 

 

 

Add 5% wastage

0.02

cft

 

 

 

 

 

 

 

 

 

0.33

cft

@

Tk.

2,000.00

per cft

 

 

 

 

 

Using 10 times

@

Tk.

200.00

per cft

=

Tk.

66.00

  1.  

Labour for shuttering

 

 

 

 

 

 

 

 

 

 

2 x 4 x 5'-0" x 1.5" =

5

sft

@

Tk.

2.50

per sft

=

Tk.

12.50

 

 

 

 

 

 

 

Sub - Total

=

Tk.

4,684.44

 

 

 

 

 

Profit

10.00%

=

Tk.

468.44

 

 

 

 

 

Overhead

3.50%

=

Tk.

163.96

 

 

 

 

 

 

 

Total

=

Tk.

5,316.84

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

339.37

 

 

 

 

 

 

 

Grand Total

=

Tk.

5,656.21

(i)

Ground floor

 

 

 

 

 

Rate per sft

=

Tk.

56.56

 

 

 

 

 

 

 

Rate per sqm

=

Tk.

608.81

 

 

 

 

Say,

Tk.

609

.00 per sqm