NEED4ENGINEER.COM , ২০১১ সাল থেকে অলাভজনক ভাবে নির্মাণ কাজের বিভিন্ন বিষয় নিয়ে সেবা দিয়ে যাচ্ছে। এ্যাড না দেখতে লগিন করুন
Prev Next


07.4.4 Cost of concrete for cornice, railing, drop walls, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground

floor

Considering 100 cft

  1. Materials (From Secondary Input : Item B-6) = Tk. 28,198.75
  2. Laying/placing concrete (@ 600 cft concreting using 1 mixer machine in one day) = Tk. 1,999.67

(From Secondary Input : Item A-4) Sub - Total Tk. 30,198.42

Profit 10.00% = Tk. 3,019.84

Overhead 3.50% = Tk. 1,056.94

Total = Tk. 34,275.20

Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,187.78

Grand Total = Tk. 36,462.98

Rate per cft = Tk. 364.63

Rate per cum = Tk. 12,876.91

Say, Tk. 12,877 .00 per cum

 

Item No.- 07.5

R.C.C work (1:1.:2) complete excluding the cost of reinforcement and its fabrication with stone chips & admixture

07.5.1 Cost of concrete for individual and combined footings, pile cap, raft/mat Floor slab, foundation beam up to plinth level

Considering 100 cft

  1. Materials (From Secondary Input : Item B-7) = Tk. 29,300.00
  2. Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) = Tk. 999.83

(From Secondary Input : Item A-1) Sub - Total Tk. 30,299.83

Profit 10.00% = Tk. 3,029.98

Overhead 3.50% = Tk. 1,060.49

Total = Tk. 34,390.30

Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,195.13

Grand Total = Tk. 36,585.43

Rate per cft = Tk. 365.85

Rate per cum = Tk. 12,919.99

Say, Tk. 12,920 .00 per cum

07.5.2 Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor

Considering 100 cft

  1. Materials (From Secondary Input : Item B-7) = Tk. 29,300.00
  2. Laying/placing concrete (@ 800 cft concreting using 1 mixer machine in one day) = Tk. 1,499.75

(From Secondary Input : Item A-2) Sub - Total Tk. 30,799.75

Profit 10.00% = Tk. 3,079.98

Overhead 3.50% = Tk. 1,077.99

Total = Tk. 34,957.72

Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,231.34

Grand Total = Tk. 37,189.06

Rate per cft = Tk. 371.89

Rate per cum = Tk. 13,133.30

Say, Tk. 13,134 .00 per cum

 

Item No.- 07.6

Fair-face concrete (1:1.5:3) complete excluding the cost of reinforcement and its fabrication with stone chips, grey cement, white cement & admixture

07.6.1 Cost of concrete for column, wall, beam,

slab, Consiering drop wall, 100 corncft

  1. Materials (From Secondary Input : Item B-8) = Tk. 33,210.00
  2. Laying/placing concrete (@ 500 cft concreting using 1 mixer machine in one day) = Tk. 2,399.60

(From Secondary Input : Item A-4) Sub - Total Tk. 35,609.60

Profit 10.00% = Tk. 3,560.96

Overhead 3.50% = Tk. 1,246.34

Total = Tk. 40,416.90