07.4.4 Cost of concrete for cornice, railing, drop walls, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground |
floor Considering 100 cft
|
(From Secondary Input : Item A-4) Sub - Total Tk. 30,198.42 Profit 10.00% = Tk. 3,019.84 Overhead 3.50% = Tk. 1,056.94 |
Total = Tk. 34,275.20 Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,187.78 |
Grand Total = Tk. 36,462.98 Rate per cft = Tk. 364.63 Rate per cum = Tk. 12,876.91 |
Say, Tk. 12,877 .00 per cum |
|
Item No.- 07.5 |
R.C.C work (1:1.:2) complete excluding the cost of reinforcement and its fabrication with stone chips & admixture 07.5.1 Cost of concrete for individual and combined footings, pile cap, raft/mat Floor slab, foundation beam up to plinth level |
Considering 100 cft
|
(From Secondary Input : Item A-1) Sub - Total Tk. 30,299.83 Profit 10.00% = Tk. 3,029.98 Overhead 3.50% = Tk. 1,060.49 |
Total = Tk. 34,390.30 Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,195.13 |
Grand Total = Tk. 36,585.43 Rate per cft = Tk. 365.85 Rate per cum = Tk. 12,919.99 |
Say, Tk. 12,920 .00 per cum |
07.5.2 Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor |
Considering 100 cft
|
(From Secondary Input : Item A-2) Sub - Total Tk. 30,799.75 Profit 10.00% = Tk. 3,079.98 Overhead 3.50% = Tk. 1,077.99 |
Total = Tk. 34,957.72 Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,231.34 |
Grand Total = Tk. 37,189.06 Rate per cft = Tk. 371.89 Rate per cum = Tk. 13,133.30 |
Say, Tk. 13,134 .00 per cum |
|
Item No.- 07.6 |
Fair-face concrete (1:1.5:3) complete excluding the cost of reinforcement and its fabrication with stone chips, grey cement, white cement & admixture 07.6.1 Cost of concrete for column, wall, beam, |
slab, Consiering drop wall, 100 corncft
|
(From Secondary Input : Item A-4) Sub - Total Tk. 35,609.60 Profit 10.00% = Tk. 3,560.96 Overhead 3.50% = Tk. 1,246.34 |
Total = Tk. 40,416.90 |