Prev Next
īģŋ

  1.  

Cost of local sand as loading

 

 

 

 

 

 

 

 

materials (taking 2 times use) 3645.715

cft

@

Tk. 450.00

per % cft

=

Tk.

16,405.72

  1.  

Labour for bag filling,

stitching, loading & unloading: 7291.43

bags

@

Tk. 10.00

per bag

=

Tk.

72,914.30

  1.  

Preparation of result in

 

 

 

 

 

 

 

 

standard form in triplicate 1

test

@

Tk. 6,000.00

per test

=

Tk.

6,000.00

  1.  

Other incidental charges

 

 

 

LS

=

Tk.

1,600.00

 

 

 

 

 

Sub - Total

=

Tk.

185,988.60

 

 

 

 

Profit

10.00%

=

Tk.

18,598.86

 

 

 

 

Overhead

3.50%

=

Tk.

6,509.60

 

 

 

 

 

Total

=

Tk.

211,097.06

 

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

13,474.28

 

 

 

 

 

Grand Total

=

Tk.

224,571.34

 

 

 

Say,

Tk. 224,571

. 00 per test

 

 

 

 

Tk. 1,123 per Mton test

 

09.8.7

 

 

 

 

 

 

 

 

 

For 250 tonne load for 1 No. test 250

290

Mton

(working volume)

 

 

 

 

 

sand =

9114.29

bags

 

Wt of sand =

35

 

kg/bag

(d)

Platform making: crib wall

per ton

 

Tk. 275.00

 

 

Tk.

68,750.00

  1.  

Foreman 2

nos

@

Tk. 800.00

each

=

Tk.

1,600.00

  1.  

Skilled labour 8

nos

@

Tk. 390.00

each

=

Tk.

3,120.00

  1.  

Ordinary labour 16

nos

@

Tk. 320.00

each

=

Tk.

5,120.00

  1.  

Hire charge of load testing equipment (joist,

jacks and other necessary devices in/c 1
caliberation charges, hydraulic fluid etc.)

test

@

Tk. 8,000.00

per test

=

Tk.

8,000.00

  1.  

Cost of empty gunny bags

 

 

 

 

 

 

 

 

(taking 2 times use) 4557.145

bags

@

Tk. 5.00

per bag

=

Tk.

22,785.73

  1.  

Cost of local sand as loading

 

 

 

 

 

 

 

 

materials (taking 2 times use) 4557.145

cft

@

Tk. 450.00

per % cft

=

Tk.

20,507.15

  1.  

Labour for bag filling,

stitching, loading & unloading: 9114.29

bags

@

Tk. 10.00

per bag

=

Tk.

91,142.90

  1.  

Preparation of result in standard

 

 

 

 

 

 

 

 

form in triplicate 1

test

@

Tk. 6,000.00

per test

=

Tk.

6,000.00

  1.  

Other incidental charges

 

 

 

LS

=

Tk.

1,600.00

 

 

 

 

 

Sub - Total

=

Tk.

228,625.78

 

 

 

 

Profit

10.00%

=

Tk.

22,862.58

 

 

 

 

Overhead

3.50%

=

Tk.

8,001.90

 

 

 

 

 

Total

=

Tk.

259,490.26

 

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

16,563.21

 

 

 

 

 

Grand Total

=

Tk.

276,053.47

 

 

 

Say,

Tk. 276,053

. 00 per test

 

 

 

 

Tk. 1,104.21 per Mton test

 

09.8.8

 

 

 

 

 

 

 

 

 

For 300 tonne load for 1 No. of test 300

348

Mton

(working volume)

 

 

 

 

 

sand =

10937.14

bags

 

Wt of sand =

35

 

kg/bag

(b)

Platform making: crib wall

per ton

 

Tk. 275.00

 

 

Tk.

82,500.00

  1.  

Foreman 2

nos

@

Tk. 800.00

each

=

Tk.

1,600.00

  1.  

Skilled labour 8

nos

@

Tk. 390.00

each

=

Tk.

3,120.00

  1.  

Ordinary labour 16

nos

@

Tk. 320.00

each

=

Tk.

5,120.00

(c)

Hire charge of load testing equipment (joist, jacks and other necessary devices in/c caliberation

 

 

 

 

 

 

 

 

charges, hydraulic fluid etc.) 1

test

@

Tk. 8,000.00

per test

=

Tk.

8,000.00

(d)

Cost of empty gunny bags

 

 

 

 

 

 

 

 

(taking 2 times use) 5468.57

bags

@

Tk. 5.00

per bag

=

Tk.

27,342.85

(e)

Cost of local sand as loading

 

 

 

 

 

 

 

 

materials (taking 2 times use) 5468.57

cft

@

Tk. 450.00

per % cft

=

Tk.

24,608.57

(f)

Labour for bag filling,