Cost of local sand as loading |
|
|
|
|
|
|
| |
| materials (taking 2 times use) 3645.715 | cft | @ | Tk. 450.00 | per % cft | = | Tk. | 16,405.72 |
Labour for bag filling, stitching, loading & unloading: 7291.43 | bags | @ | Tk. 10.00 | per bag | = | Tk. | 72,914.30 | |
Preparation of result in |
|
|
|
|
|
|
| |
| standard form in triplicate 1 | test | @ | Tk. 6,000.00 | per test | = | Tk. | 6,000.00 |
Other incidental charges |
|
|
| LS | = | Tk. | 1,600.00 | |
|
|
|
|
| Sub - Total | = | Tk. | 185,988.60 |
|
|
|
| Profit | 10.00% | = | Tk. | 18,598.86 |
|
|
|
| Overhead | 3.50% | = | Tk. | 6,509.60 |
|
|
|
|
| Total | = | Tk. | 211,097.06 |
| Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 13,474.28 | ||
|
|
|
|
| Grand Total | = | Tk. | 224,571.34 |
|
|
| Say, | Tk. 224,571 | . 00 per test |
|
|
|
| Tk. 1,123 per Mton test |
| ||||||
09.8.7 |
|
|
|
|
|
|
|
|
| For 250 tonne load for 1 No. test 250 | 290 | Mton | (working volume) |
|
|
|
|
| sand = | 9114.29 | bags |
| Wt of sand = | 35 |
| kg/bag |
(d) | Platform making: crib wall | per ton |
| Tk. 275.00 |
|
| Tk. | 68,750.00 |
Foreman 2 | nos | @ | Tk. 800.00 | each | = | Tk. | 1,600.00 | |
Skilled labour 8 | nos | @ | Tk. 390.00 | each | = | Tk. | 3,120.00 | |
Ordinary labour 16 | nos | @ | Tk. 320.00 | each | = | Tk. | 5,120.00 | |
Hire charge of load testing equipment (joist, jacks and other necessary devices in/c 1 | test | @ | Tk. 8,000.00 | per test | = | Tk. | 8,000.00 | |
Cost of empty gunny bags |
|
|
|
|
|
|
| |
| (taking 2 times use) 4557.145 | bags | @ | Tk. 5.00 | per bag | = | Tk. | 22,785.73 |
Cost of local sand as loading |
|
|
|
|
|
|
| |
| materials (taking 2 times use) 4557.145 | cft | @ | Tk. 450.00 | per % cft | = | Tk. | 20,507.15 |
Labour for bag filling, stitching, loading & unloading: 9114.29 | bags | @ | Tk. 10.00 | per bag | = | Tk. | 91,142.90 | |
Preparation of result in standard |
|
|
|
|
|
|
| |
| form in triplicate 1 | test | @ | Tk. 6,000.00 | per test | = | Tk. | 6,000.00 |
Other incidental charges |
|
|
| LS | = | Tk. | 1,600.00 | |
|
|
|
|
| Sub - Total | = | Tk. | 228,625.78 |
|
|
|
| Profit | 10.00% | = | Tk. | 22,862.58 |
|
|
|
| Overhead | 3.50% | = | Tk. | 8,001.90 |
|
|
|
|
| Total | = | Tk. | 259,490.26 |
| Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 16,563.21 | ||
|
|
|
|
| Grand Total | = | Tk. | 276,053.47 |
|
|
| Say, | Tk. 276,053 | . 00 per test |
|
|
|
| Tk. 1,104.21 per Mton test |
| ||||||
09.8.8 |
|
|
|
|
|
|
|
|
| For 300 tonne load for 1 No. of test 300 | 348 | Mton | (working volume) |
|
|
|
|
| sand = | 10937.14 | bags |
| Wt of sand = | 35 |
| kg/bag |
(b) | Platform making: crib wall | per ton |
| Tk. 275.00 |
|
| Tk. | 82,500.00 |
Foreman 2 | nos | @ | Tk. 800.00 | each | = | Tk. | 1,600.00 | |
Skilled labour 8 | nos | @ | Tk. 390.00 | each | = | Tk. | 3,120.00 | |
Ordinary labour 16 | nos | @ | Tk. 320.00 | each | = | Tk. | 5,120.00 | |
(c) | Hire charge of load testing equipment (joist, jacks and other necessary devices in/c caliberation |
|
|
|
|
|
|
|
| charges, hydraulic fluid etc.) 1 | test | @ | Tk. 8,000.00 | per test | = | Tk. | 8,000.00 |
(d) | Cost of empty gunny bags |
|
|
|
|
|
|
|
| (taking 2 times use) 5468.57 | bags | @ | Tk. 5.00 | per bag | = | Tk. | 27,342.85 |
(e) | Cost of local sand as loading |
|
|
|
|
|
|
|
| materials (taking 2 times use) 5468.57 | cft | @ | Tk. 450.00 | per % cft | = | Tk. | 24,608.57 |
(f) | Labour for bag filling, |
|
|
|
|
|
|
|