|
| Sub - Total | = | Tk. | 350,537.19 |
| Profit 10.00% | = | Tk. | 35,053.72 | |
|
| Overhead 3.50% | = | Tk. | 12,268.80 |
|
| Total | = | Tk. | 397,859.71 |
Add VAT with adjustment factor |
| 1.06383 6.00% | = | Tk. | 25,395.31 |
|
| Grand Total | = | Tk. | 423,255.02 |
Say, Tk. |
| 423,255 . 00 per test |
|
|
|
Tk. |
| 1,058 per Mton test |
|
|
|
Item No.- 09.9 |
|
|
|
|
|
9.9.1 For intermediate loading from 50 tonne to 100 tonne for each additional tonne |
| per tonne |
| Tk. | 1,349 |
9.9.2 For intermediate loading from 100 tonne to 150 tonne for each additional tonne. |
| per tonne |
| Tk. | 1,193 |
9.9.3 For intermediate loading from 150 tonne to 200 tonne for each additional tonne. |
| per tonne |
| Tk. | 1,138 |
9.9.4 For intermediate loading from 200 tonne to 250 tonne for each additional tonne. |
| per tonne |
| Tk. | 1,114 |
9.9.5 For intermediate loading from 250 tonne to 300 tonne for each additional tonne. |
| per tonne |
| Tk. | 1,094 |
9.9.6 For intermediate loading from 300 tonne to 350 tonne for each additional tonne. |
| per tonne |
| Tk. | 1,077 |
9.9.7 For intermediate loading from 350 tonne to 400 tonne for each additional tonne. |
| per tonne |
| Tk. | 1,064 |
Item No.- 09.10.1 |
|
|
|
|
|
10" x 10" Pre-cast pile with reinforced cement concrete (1 : 1.25 : 2.5) with stone chips. |
|
|
|
|
|
Considering 40 rft long 10" x 10" size pile |
|
|
|
|
|
Also Considering 100 rft pile making work using 100 cft concrete |
|
|
|
|
|
|
|
| = | Tk. | 28,198.75 |
|
|
| = | Tk. | 1,199.80 |
|
|
|
|
|
|
Volume of concrete: |
|
|
|
|
|
11 x 10" x 10" x 40'-0" = 305.56 cft (a) Cost of shuttering: |
|
|
|
|
|
|
|
|
|
|
|
Sides: 1 x 12 x 40'-0" x 0'-10"= 400.00 sft |
|
|
|
|
|
Add wastage 5%= 20.00 sft |
| 27.44 per Ib | = | Tk. | 35,150.64 |
= 420.00 sft @ 3.05 Ib per sft= 1281.00 Ibs @ Tk.
| |||||
Sides: 2 x 12 x 40'-0"= 960.00 rft |
|
|
|
|
|
Vertical: 12 x 41 x 1'-0"= 492.00 rft |
|
|
|
|
|
= 1452.00 rft | |||||
Add wastage 5%= 72.60 rft |
| 24.94 per Ib | = | Tk. | 68,062.01 |
1524.60 rft @ 1.79 Ib per rft = 2729.03 Ibs @ Tk.
| |||||
Stiffner: 6 x 20 x 1'-2" = 140.00 rft |
|
|
|
|
|
Clamps: 6 x 12 x 6"= 36.00 rft |
|
|
|
|
|
= 176.00 rft | |||||
Add 5% wastage= 8.8 rft |
| 24.94 per Ib | = | Tk. | 4,406.15 |
= 184.80 rft @ 0.956 Ibs per rft= 176.67 Ibs @ Tk. | |||||
|
| 160.00 per kg | = | Tk. | 3,200.00 |
12 x 40'-0" x 0'-10"= 400.00 sft @ Tk. |
| 75.00 per sft | = | Tk. | 30,000.00 |
|
| Total | = | Tk. | 140,818.80 |
in position as required 400.00 sft @ Tk.
shutter water-proof. 400.00 sft @ Tk. |
| Using 16 times 10.00 per sft 1.25 per sft | = = = | Tk. | 8,801.18 4,000.00 500.00 |
|
| 2.67 per sft | = | Tk. | 1,068.00 |
|
| Total for 305.56 cft | = | Tk. | 14,369.18 |
|
| Cost for 100 cft | = | Tk. | 4,702.57 |