Item No.- 09.10.5 |
|
|
|
|
|
18" x 18" Pre-cast pile with reinforced cement concrete (1 : 1.25 : 2.5) with stone chips. |
|
|
|
|
|
Considering 60 rft long 18" x 18" size pile |
|
|
|
|
|
Also considering 44.44 rft long pile making work using 100 cft concrete |
|
|
|
|
|
A. Cost of concrete materials |
|
| = | Tk. | 28,198.75 |
B. Labour, machinery, fuel & lubricants for casting |
|
| = | Tk. | 1,199.80 |
C. Cost of shuttering for 11 No. of pile |
|
|
|
|
|
Volume of concrete: |
|
|
|
|
|
11 x 18" x 18" x 60'-0" = 1485 cft (a) Cost of shuttering: |
|
|
|
|
|
|
|
|
|
|
|
Sides: 16 x 60'-0" x 1'-6"= 1440.00 sft |
|
|
|
|
|
Add wastage 5%= 72.00 sft | 27.44 | per Ib | = | Tk. | 126,542.30 |
= 1512.00 sft @ 3.05 Ib per sft= 4611.60 Ibs @ Tk.
| |||||
Sides: 2 x 12 x 55'-0"= 1540.00 rft |
|
|
|
|
|
Supports: 12 x 61x 1'-6"= 1098.00 rft |
|
|
|
|
|
= 2638.00 rft | |||||
Add wastage 5%= 131.90 rft | 24.94 | per Ib | = | Tk. | 123,655.51 |
2769.90 rft @ 1.79 Ib per rft= 4958.12 Ibs @ Tk.
| |||||
Stiffner: 6 x 25 x 1'-2"= 175.00 rft |
|
|
|
|
|
Clamps: 6 x 16 x 6"= 48.00 rft |
|
|
|
|
|
= 223.00 rft | |||||
Add 5% wastage= 11.15 rft | 24.94 | per Ib | = | Tk. | 5,582.82 |
= 234.15 rft @ 0.956 Ibs per rft= 223.85 Ibs @ Tk. | |||||
| 160.00 | per kg | = | Tk. | 4,000.00 |
2 x 6 x 60 x 1'-6" 1080.00 sft @ Tk. | 75.00 | per sft | = | Tk. | 81,000.00 |
|
| Total | = | Tk. | 340,780.63 |
in position as required 1080.00 sft @ Tk.
shutter water proof 1080.00 sft @ Tk. | Using 16 times 10.00 per sft 1.25 per sft | = = = | Tk. | 21,298.79 10,800.00 1,350.00 | |
| 2.67 | per sft | = | Tk. | 1,281.60 |
|
| Total | = | Tk. | 33,448.79 |
| Cost for 100 cft of work | = | Tk. | 2,252.44 | |
D. Cost of bed preparation: |
|
|
|
|
|
Area of bed: 1 x 65'-0" x 19'-0"= 1235.00 sft
with neat cement finishing 1235.00 sft @ Tk. | 0.32 21.58 | per sft | = = | Tk. Tk. | 395.20 26,651.30 |
|
| Total | = | Tk. | 27,046.50 |
| Cost for 100 cft of work | = | Tk. | 1,821.31 | |
| Using 8 times | = | Tk. | 227.66 | |
E. Polythene as separator between pile layers during casting concrete 1235.00 sft @ Tk. | 319.44 per % sft | = | Tk. | 3,945.08 | |
| Cost for 100 cft of work | = | Tk. | 265.66 | |
Abstract of cosr for 100 cft of work |
|
|
|
|
|
|
|
| = | Tk. | 28,198.75 |
|
|
| = | Tk. | 1,199.80 |
|
|
| = | Tk. | 2,252.44 |
|
|
| = | Tk. | 227.66 |
|
|
| = | Tk. | 265.66 |
|
| Sub - Total | = | Tk. | 32,144.31 |
| Profit | 10.00% | = | Tk. | 3,214.43 |