| Overhead | 3.50% | = | Tk. | 375.20 |
Total | = | Tk. | 12,167.20 | ||
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 776.63 |
|
| Grand Total | = | Tk. | 12,943.83 |
|
| Rate per rft | = | Tk. | 123.27 |
|
| Rate per meter | = | Tk. | 404.45 |
Say, Tk. | 404 | .00 per meter |
|
|
|
|
|
|
|
|
|
Item No.- 09.14 |
|
|
|
|
|
Driving of (12" x 12") size pre-cast pile with drop hammer type rig. |
|
|
|
|
|
Considering driving 40 rft 02 nos of Pile
in/c cost of fuel and lubricant etc. 1 day @ Tk.
| 5,500.00 600.00 | per day | = = | Tk. Tk. | 5,500.00 600.00 |
| 390.00 | each | = | Tk. | 780.00 |
| 320.00 | each | = | Tk. | 3,840.00 |
|
| Sub - Total | = | Tk. | 10,720.00 |
| Profit | 10.00% | = | Tk. | 1,072.00 |
| Overhead | 3.50% | = | Tk. | 375.20 |
|
| Total | = | Tk. | 12,167.20 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 776.63 |
|
| Grand Total | = | Tk. | 12,943.83 |
|
| Rate per rft | = | Tk. | 161.80 |
|
| Rate per meter | = | Tk. | 530.87 |
Say, Tk. | 531 | .00 per meter |
|
|
|
|
|
|
|
|
|
Item No.- 09.15 |
|
|
|
|
|
Driving of (14" x 14") size pre-cast pile with drop hammer type rig |
|
|
|
|
|
Considering driving 40 rft 1.5 No pile
in/c cost of fuel and lubricant etc. 1 day @ Tk. | 5,500.00 | per day | = | Tk. | 5,500.00 |
| 600.00 | each | = | Tk. | 600.00 |
| 390.00 | each | = | Tk. | 780.00 |
| 320.00 | each | = | Tk. | 3,840.00 |
|
| Sub - Total | = | Tk. | 10,720.00 |
| Profit | 10.00% | = | Tk. | 1,072.00 |
| Overhead | 3.50% | = | Tk. | 375.20 |
|
| Total | = | Tk. | 12,167.20 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 776.63 |
|
| Grand Total | = | Tk. | 12,943.83 |
|
| Rate per rft | = | Tk. | 215.73 |
|
| Rate per meter | = | Tk. | 707.81 |
Say, Tk. | 708 | .00 per meter |
|
|
|
|
|
|
|
|
|
Item No.- 09.16 |
|
|
|
|
|
Mobilization and demobilzation of automatic diesel hammer mounted complete rig set. 1 Truck fare (2 x 5 trips) in/c loading & unloading 10 trips @ Tk. | 15,000.00 | per trip | = | Tk. | 150,000.00 |
|
| Sub - Total | = | Tk. | 150,000.00 |
| Profit | 10.00% | = | Tk. | 15,000.00 |
| Overhead | 3.50% | = | Tk. | 5,250.00 |
|
| Total | = | Tk. | 170,250.00 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 10,867.02 |
|
| Grand Total | = | Tk. | 181,117.02 |
Say, Tk. | 181,117 .00 per set |
|
|
| |