Item No.- 10.7 |
Supply of GP Purlin / Girt Considering 1000 Kg of work (i) Cost of materials a) GP sheet with 2% wastage 1020 Kg @ Tk. 98,000.00 per ton = Tk. 99,960.00 (ii) Cost of fabrication and carriage
(iii) Erection Tk. 4.00 per kg = Tk. 4,000.00 |
Sub - Total = Tk. 112,960.00 Profit 10.00% = Tk. 11,296.00 Overhead 3.50% = Tk. 3,953.60 |
Total = Tk. 128,209.60 Add VAT with adjustment factor 1.06383 6.00% = Tk. 8,183.59 |
Grand Total = Tk. 136,393.19 Rate per kg = Tk. 136.39 |
Say, Tk. 137 .00 per kg |
|
Item No.- 10.8 |
Supplying & fixing of sag rod conforming of Grade: 40, Fy = 34.5 KN/cm2, including the cost of making threads, nuts and washers, red oxide primer etc. all complete as per design and drawing direction Engineer-In-Charge Considering 100 Kg of work (i) Cost of materials
(ii) Cost of fabrication and carriage
(iii) Erection Tk. 10.00 per kg = Tk. 1,000.00 |
Sub - Total = Tk. 10,441.00 Profit 10.00% = Tk. 1,044.10 Overhead 3.50% = Tk. 365.44 |
Total = Tk. 11,850.54 Add VAT with adjustment factor 1.06383 6.00% = Tk. 756.42 |
Grand Total = Tk. 12,606.96 Rate per kg = Tk. 126.07 |
Say, Tk. 127 .00 per kg |
|
Item No.- 10.9 |
Supplying & fixing of cable/ wire bracing according to "ASTM A475" Fy = 119.3 KN/cm2 with U bolt and hilt washer as per design and drawing all complete and instruction of Engineer-In-Charge Considering 100 meter work (i) Cost of materials
(ii) Cost of fabrication and carriage a) Local carriage, load-unload 171.21 kg @ Tk. 1,500.00 per ton = Tk. 256.82 (iii) Erection Tk. 10.00 per kg = Tk. 1,712.10 |
Sub - Total = Tk. 17,718.92 Profit 10.00% = Tk. 1,771.89 Overhead 3.50% = Tk. 620.16 |
Total = Tk. 20,110.97 Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,283.68 |
Grand Total = Tk. 21,394.65 Rate per meter = Tk. 213.95 |
Say, Tk. 214 .00 per meter |