Item No.- 10.16

Supply and application of 2-coat enamel paint to surface of steel structural members including the cost of surface cleaning, finishing etc. all

complete and instruction of Engineer-In-Charge. (payment shall be made on strucutral steel weight basis)

(i) Cost of materials for 1000 kg work

  1. Primer and Finish Paint (1+1) 12 litre @ Tk. 270.00 per litre = Tk. 3,240.00
  2. Local carriage, load-unload LS = Tk. 200.00

(ii) Labour charge for cleaning and application Tk. 3,500.00 per ton = Tk. 3,500.00
of paint

Sub - Total = Tk. 6,940.00

Profit 10.00% = Tk. 694.00

Overhead 3.50% = Tk. 242.90

Total = Tk. 7,876.90

Add VAT with adjustment factor 1.06383 6.00% = Tk. 502.78

Grand Total = Tk. 8,379.68

Rate per kg = Tk. 8.38

Say, Tk. 9 .00 per kg

 

Item No.- 10.17

Corrosion Protection paint for structural steel members: Steel members will be shot blasted inside the enclosed shot blasting machine conforming SA 2.5 and painted for corrosio protection as per the technical specification of the tender document and direction of engineer in

ch Cost of materials for 1000 kg work

A.

  1. Primer and Finish Paint (1+1) 18 litre @ Tk. 950.00 per litre = Tk. 17,100.00
  2. Local carriage, load-unload LS = Tk. 200.00

B. Labour charge for cleaning and application Tk. 3,500.00 per ton = Tk. 3,500.00
of paint

Sub - Total = Tk. 20,800.00

Profit 10.00% = Tk. 2,080.00

Overhead 3.50% = Tk. 728.00

Total = Tk. 23,608.00

Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,506.89

Grand Total = Tk. 25,114.89

Rate per kg = Tk. 25.11

Say, Tk. 26 .00 per kg

 

Item No.- 10.18

Supply of Non-Shrink Grout to steel column bases conforming to ASTM C 109 having compressive strength not less than 45 MPa including shutter and all accessories and as per direction of engineer in charge

(i) Cost of materials for 1.0 cum work

  1. cost of non shrink grout 78 bag @ Tk. 1,500.00 per bag = Tk. 117,000.00
  2. Local carriage, load-unload Tk. 1,500.00 per truck = Tk. 1,500.00

(ii) Labour charge for shuttering and application Tk. 1,764.00 per cum = Tk. 1,764.00
of non-shrink grout

Sub - Total = Tk. 120,264.00

Profit 10.00% = Tk. 12,026.40

Overhead 3.50% = Tk. 4,209.24

Total = Tk. 136,499.64

Add VAT with adjustment factor 1.06383 6.00% = Tk. 8,712.74

Grand Total = Tk. 145,212.38

Rate per cum = Tk. 145,212.38

Say, Tk. 145,213 .00 per cum

 

Item No.- 10.19.1

Galvanized iron plain sheet ridging with galvanized bolts and nuts Considering 9.1 (30 rft) meter. of work

  1. Price considering 10% laping 10.010 rm @ Tk. 191.39 per rm = Tk. 1,915.81
  2. Screws, limpet, washer etc. 15% = Tk. 287.37
  3. Carpenter 1 no @ Tk. 600.00 each = Tk. 600.00
  4. Helper to carpenter 1 no @ Tk. 390.00 each = Tk. 390.00

Sub - Total = Tk. 3,193.18