DIVISION 11. WOOD WORKS IN DOOR AND WINDOW FRAME, ROOF TRUSS AND RAILINGS |
| ||||||
|
|
|
|
|
|
|
|
Item No.- 11.1.1 |
|
|
|
|
|
|
|
Supply and making door and window frames with seasoned wood Considering 1 No. door frame Considering for door size: 3'-4" x 7'-0" Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-5" = 1.5 cft (finished) = (2 x 7'-0" + 3'-6") x 0'-2.75" x 0'-5.25" = 1.75 cft (gross) |
|
|
|
|
|
|
|
For Mehgoni (a) Cost of wood 1.75 cft | @ | Tk. | 1,800.00 | per cft | = | Tk. | 3,150.00 |
(b) Coaltaring: 2 coats 7.5 sft (c) Labour for making frame
| @ @ | Tk. Tk. | 7.00 600.00 | per sft | = = | Tk. Tk. | 52.50 450.00 |
| @ | Tk. | 390.00 | per day | = | Tk. | 390.00 |
(d) Labour for fitting, fixing in position |
|
|
| LS | = | Tk. | 195.00 |
|
|
|
| Sub - Total | = | Tk. | 4,237.50 |
|
|
| Profit | 10.00% | = | Tk. | 423.75 |
|
|
| Overhead | 3.50% | = | Tk. | 148.31 |
|
|
|
| Total | = | Tk. | 4,809.56 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 306.99 | |
|
|
|
| Grand Total | = | Tk. | 5,116.55 |
|
|
|
| Rate per cft | = | Tk. | 3,411.03 |
|
|
|
| Rate per cum | = | Tk. | 120,460.52 |
| Say, | Tk. | 120,461 | .00 per cum |
|
|
|
|
|
|
|
|
|
|
|
Item No.- 11.1.2 |
|
|
|
|
|
|
|
Supply and making door and window frames with seasoned wood |
|
|
|
|
|
|
|
Considering 1 No. door frame |
|
|
|
|
|
|
|
Considering for door size: 3'-4" x 7'-0" |
|
|
|
|
|
|
|
Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-5" =1.5 cft (finished) |
|
|
|
|
|
|
|
= (2 x 7'-0" + 3'-6") x 0'-2.75" x 0'-5.25" = 1.75 (gross) |
|
|
|
|
|
|
|
Garjan/Jam / local sal wood (a) Cost of wood 1.75 cft (b) Coaltaring: 2 coats 1 x (2 x 7'-2.5" + 3'-4") x 0'-5"= 7.5 sft | @ @ | Tk. Tk. | 2,000.0 7.00 | per cft | = = | Tk. Tk. | 3,500.00 52.50 |
(c) Labour for making frame |
|
|
|
| = |
|
|
| @ | Tk. | 600.00 | per day | = | Tk. | 450.00 |
| @ | Tk. | 390.00 | per day | = | Tk. | 390.00 |
(d) Labour for fitting, fixing in position |
|
|
| LS | = | Tk. | 195.00 |
|
|
|
| Sub - Total | = | Tk. | 4,587.50 |
|
|
| Profit | 10.00% | = | Tk. | 458.75 |
|
|
| Overhead | 3.50% | = | Tk. | 160.56 |
|
|
|
| Total | = | Tk. | 5,206.81 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 332.35 | |
|
|
|
| Grand Total | = | Tk. | 5,539.16 |
|
|
|
| Rate per cft | = | Tk. | 3,692.77 |
|
|
|
| Rate per cum | = | Tk. | 130,410.17 |
| Say, | Tk. | 130,410 | .00 per cum |
|
|
|
|
|
|
|
|
|
|
|
Item No.- 11.1.3 |
|
|
|
|
|
|
|
Supply and making door and window frames with seasoned wood |
|
|
|
|
|
|
|
Considering 1 No. door frame |
|
|
|
|
|
|
|
Considering for door size: 3'-4" x 7'-0" |
|
|
|
|
|
|
|
Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-5" = 1.5 cft (finished) |
|
|
|
|
|
|
|
= (2 x 7'-0" + 3'-6") x 0'-2.75" x 0'-5.25" = 1.75 cft (gross) |
|
|
|
|
|
|
|
For Silkarai (a) Cost of wood 1.75 cft | @ | Tk. | 2,490.0 | per cft | = | Tk. | 4,357.50 |
(i) Carpenter 0.75 no | @ @ | Tk. Tk. | 7.00 600.00 | per sft | = = | Tk. Tk. | 52.50 450.00 |