Item No.- 14.1.1

 

 

 

 

Supplying, fitting and fixing Aluminium Swing door with spandrel (S.S colour/Black Colour) Considering 1 No. door

Considering: 4'-0" x 6'-10"= 27.32 sft of work

(A) Cost of aluminium section:

1. 101.60 mm, 44.45 mm wall frame of 1.2 mm thick

2 x 6'-10" = 13.66 rft @ Tk. 122.00

per rft

=

Tk.

1,666.52

2. 54 mm, 46 mm wall frame of 1.8 mm shutter side of 2.3 mm thick

2 x 6'-10" = 13.66 rft @ Tk.

133.00

per rft

=

Tk.

1,816.78

3. 16.54 mm, 15.49 mm door glass bit of 0.99 mm thick

2 x 2 x 6'-1"= 24.32 rft

2 x 4 x 3'-3"= 26.00 rft

16.00

per rft

=

Tk.

805.12

= 50.32 rft @ Tk.

4. 101.54 mm, 42.93 mm closure section of 1.8 mm thick

1 x 3'-81/2"= 3.71 rft @ Tk.

134.00

per rft

=

Tk.

497.14

5. 101.60 mm closure cover of 1.5 mm thick

1 x 3'-81/2"= 3.71 rft @ Tk.

47.00

per rft

=

Tk.

174.37

6. 101.60 mm, 12.70 mm floor bottom of 4 mm thick

1 x 3'-81/2"= 3.71 rft @ Tk.

131.00

per rft

=

Tk.

486.01

7. 82.60 mm, 43.99 mm shutter bottom of 1.8 mm thick

1 x 3'-4"= 3.33 rft @ Tk.

178.00

per rft

=

Tk.

592.74

8. 51 mm, 43.99 mm shutter top of 1.8 mm thick

1 x 3'-4"= 3.33 rft @ Tk.

146.00

per rft

=

Tk.

486.18

9. 101.60 mm, 38.10 mm, 25.4 mm handle (short) of 2.3 mm, 2.3 mm, 4.01 mm thick

2 x 0'-9"= 1.5 rft @ Tk.

188.00

per rft

=

Tk.

282.00

10 31.75 mm shutter divider of 1.2 mm thick

1 x 3'-4"= 3.33 rft @ Tk.

68.00

per rft

=

Tk.

226.44

11 7.14 mm spandrel of 1.4 mm to 1.2 mm thick

1 x 20'-0" = 20 rft @ Tk.

90.00

per rft

=

Tk.

1,800.00

 

 

 

=

Tk.

8,833.30

 

Cutting wastage

3%

=

Tk.

265.00

 

 

Sub total (A)

=

Tk.

9,098.30

(B) Accessories:

 

 

 

 

 

  1. Swing door closer 1 set. @ Tk.

2,700.00

per set

=

Tk.

2,700.00

  1. Swing door lock 1 set. @ Tk.

625.00

per set

=

Tk.

625.00

  1. Swing door mohiar 13.66 rft @ Tk.

5.00

per rft

=

Tk.

68.30

  1. Bolts and screws in/c sealants

 

LS

=

Tk.

225.00

 

 

Sub total (B)

=

Tk.

3,618.30

(C) Labour charge for fabrication, assembling and fitting-fixing in position

  1. Skilled technician 3/4 no @ Tk.

1,000.00

each

=

Tk.

750.00

  1. Semi- skilled technician 3/4 no @ Tk.

600.00

each

=

Tk.

450.00

  1. Tools and plant, sundries etc.

 

LS

=

Tk.

480.00

 

 

Sub total (C)

=

Tk.

1,680.00

 

 

Total (A+B+C)

=

Tk.

14,396.60

 

Profit

10.00%

=

Tk.

1,439.66

 

Overhead

3.50%

=

Tk.

503.88

 

 

Total

=

Tk.

16,340.14

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

1,042.99

 

 

Grand Total

=

Tk.

17,383.13

 

 

Rate per sft

=

Tk.

636.28

 

 

Rate per sqm

=

Tk.

6,848.92

Say, Tk.

6,849 .00 per sqm

 

 

 

 

 

 

 

 

 

Item No.- 14.1.2

 

 

 

 

 

Supplying, fitting and fixing Aluminium Swing door with spandrel (Bronze colour)

 

 

 

 

 

Considering 1 No. door

 

 

 

 

 

Considering: 4'-0" x 6'-10"= 27.32 sft of work

(A) Cost of aluminium section:

 

 

 

 

 

1. 101.60 mm, 44.45 mm wall frame of 1.2 mm thick