2 x 1'-0" x 6" = 1 sft |
5.00 sft Add wastage 5%= 0.25 sft |
= 5.25 sft = 26.78 Ibs @ Tk. 27.44 per Ib = Tk. 734.84
2 x 0-6" x 0'-6"= 0.50 sft Add wastage 5%= 0.03 sft |
= 0.53 sft = 5.41 Ibs @ Tk. 27.44 per Ib = Tk. 148.45
2 x 5'-0" x 2'-6"= 25.00 sft Add wastage 5%= 1.25 sft |
= 26.25 sft = 53.55 Ibs @ Tk. 27.44 per Ib = Tk. 1,469.41 (b) Fittings and consumables
(c) Making steel gate in work-shop
(d) Carrying materials to work-shop & gate to site LS = Tk. 480.00 |
Sub-total = Tk. 25,756.32 (e) Work-shop charges 10% = Tk. 2,575.63 |
Total = Tk. 28,331.95 (f) Ancillary work for fitting -fixing the gate:
6 x 10" x 6" x 6"= 1.25 cft 16'-0" x 6" x 4"= 2.67 cft 2 x 4 x 6" x 4"= 1.33 cft |
5.25 cft @ Tk. 17,763.63 per % cft = Tk. 932.59 (g) Labour charge for hoisting the gate in position
|
Sub - Total = Tk. 30,962.04 Profit 10.00% = Tk. 3,096.20 Overhead 3.50% = Tk. 1,083.67 |
Total = Tk. 35,141.91 Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,243.10 |
Grand Total = Tk. 37,385.01 Rate per sft = Tk. 560.75 Rate per sqm = Tk. 6,035.91 |
Say, Tk. 6,036 .00 per sqm |
|
Item No.- 19.2.2 |
Manufacturing, supplying, fitting and fixing of security door with 7/8" dia M.S. rod and 2" x 2" x 1/4" angle frame excluding cost of painting. Considering 1 No. of gate Considering 3'-4" x 7'-0"= 23.31 sft in two parts (a) Cost of materials (i) 2" x 2" x 1/4" angle for frame: @ 3.19 Ibs per rft Vertical: 2 x 7'-0"= 14.0 rft Horizontal: 2 x 3'-4"= 6.67 rft Clamp: 4 x 1'-6"= 6.00 rft |