Prev Next
īģŋ

(e) Work-shop charges

(f) Ancillary work for fitting-fixing the gate:

  1. Making holes 6 nos @ Tk.
  2. Plain concrete: (1:2:4)

6 x 10" x 6" x 6"= 1.25 cft

16.25

Sub-total

10%

=

=

Tk. Tk.

36,214.33

3,621.43

Sub-total
each

=

=

Tk. Tk.

39,835.76

97.50

22'-0" x 6" x 4"= 3.67 cft

2 x 4 x 6" x 4"= 1.33 cft

17,763.63

500.00

per % cft
per day

=

=

Tk. Tk.

1,110.23

500.00

6.25 cft @ Tk.

(g) Labour charge for hoisting the gate in position

  1. Mason 1 no @ Tk.
  1. Mason helper 2 nos @ Tk.

390.00

per day

=

Tk.

780.00

  1. Ordinary labour 1 no @ Tk.

320.00

per day

=

Tk.

320.00

 

 

Sub - Total

=

Tk.

42,643.49

 

Profit

10.00%

=

Tk.

4,264.35

 

Overhead

3.50%

=

Tk.

1,492.52

 

 

Total

=

Tk.

48,400.36

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

3,089.39

 

 

Grand Total

=

Tk.

51,489.75

 

 

Rate per sft

=

Tk.

728.59

 

 

Rate per sqm

=

Tk.

7,842.54

Say, Tk.

7,843 .00 per sqm

 

 

 

 

 

 

 

 

 

Item No.- 19.5

 

 

 

 

 

Manufacturing, supplying, fitting and fixing of G.I. pipe gate excluding cost of painting.

 

 

 

 

 

Considering 1 No. of gate

 

 

 

 

 

Considering 10'-0" x 6'-8"= 66.67 sft in two parts

(a) Cost of materials

  1. 1.5" dia G.I. pipe

2 x 4 x 5'-0"= 40.00 rft

4 x 6'-8"= 26.67 rft

 

 

 

 

 

= 66.67 rft

Add wastage 5%= 3.33 rft

148.00

per rft

=

Tk.

10,360.00

= 70.00 rft @ Tk.

  1. 3/4" dia G.I. pipe

Vertical post: 2 x 19 x 6'-8"= 253.33 rft

 

 

 

 

 

Pocket gate: 2 x 2'-0"= 4.00 rft

2 x 4'-5"= 8.83 rft

1 x 2'-2"= 2.17 rft

 

 

 

 

 

= 268.33 rft

Add 5% wastage= 13.42 rft

70.00

per rft

=

Tk.

19,722.50

281.75 rft @ Tk.

  1. 18 BWG M.S. plate for middle part: @ 2.04 lbs per sft

2 x 5'-0" x 3'-4"= 33.33 sft

Add wastage 5%= 1.67 sft

27.44

275.00

per Ib
each

=

=

Tk. Tk.

1,959.22

550.00

= 35.00 sft

= 71.40 Ibs @ Tk.

(b) Fittings and consumables

  1. Locking arrangement 2 nos @ Tk.
  1. 5" long hinges 2 nos @ Tk.

68.00

each

=

Tk.

136.00

  1. Clamp with huskel dumney 6 nos @ Tk.

144.00

each

=

Tk.

864.00

  1. 5/8" dia M.S. socket bolt 2 nos @ Tk.

60.00

each

=

Tk.

120.00

  1. Electrodes 120 Pc. @ Tk.

(c) Making steel gate in work-shop

  1. Welder / fabricator 4 nos @ Tk.

10.00

600.00

each
per day

=

=

Tk. Tk.

1,200.00

2,400.00

  1. Helper 4 nos @ Tk.

390.00

per day

=

Tk.

1,560.00

  1. Ordinary labour 4 nos @ Tk.

320.00

per day

=

Tk.

1,280.00

(d) Carrying materials to work-shop & gate to site

 

LS

=

Tk.

480.00

 

 

Sub-total

=

Tk.

40,631.72

(e) Work-shop charges

 

10%

=

Tk.

4,063.17