Analysis of PWD SoR 2018 for Civil Works 389 |
DIVISION 20 : STAIR & VERANDAH RAILING AND STAIR NOSING |
|
Item No.- 20.1 |
Supplying, fitting and fixing of stair railing of any height with square box made with 2 nos 20 x 20 x 3 mm angle welded with each other (excluding cost of wood for hand rail). Considering 1 No. of railing Considering 9'-9" x 2'-10"= 27.6 sft exposed surface (a) Materials:
2 x 20 x 3'-1"= 122.3 rft Add wastage 5%= 6.12 rft |
= 128.42 rft = 75.1257 Ibs @ Tk. 24.94 per Ib = Tk. 1,873.63
20 x 2" x 2"= 0.56 sft Add wastage 5%= 0.03 sft |
= 0.59 sft = 6.02 Ibs @ Tk. 27.44 Per lb. = Tk. 165.19
1 x 9'-9"= 9.75 rft Add wastage 5%= 0.49 rft |
= 10.24 rft = 13.11 lbs @ Tk. 24.94 per Ib = Tk. 326.96 (b) Fittings, hardwares and consumables: (i) Electrodes with electricity: 140.00 nos @ Tk. 10.00 each = Tk. 1,400.00 (c) Labour for fabrication and making square post
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 320.00 |
Sub-total = Tk. 5,610.78 (e) Work-shop charges: 10% = Tk. 561.08 |
Sub-Total = Tk. 6,171.86 (f) Ancillary works for fitting-fixing the railing:
2" x 2" x 6" size grooves 20 nos @ Tk. 13.00 each = Tk. 260.00
(g) Labour charge for fitting fixing the stair railing
|
Sub - Total = Tk. 7,306.60 Profit 10.00% = Tk. 730.66 Overhead 3.50% = Tk. 255.73 |
Total = Tk. 8,292.99 Add VAT with adjustment factor 1.06383 6.00% = Tk. 529.34 |
Grand Total = Tk. 8,822.33 Rate per sft = Tk. 319.65 Rate per sqm = Tk. 3,440.71 |
Say, Tk. 3,441 .00 per sqm |
|
Item No.- 20.2 |
Supplying, fitting and fixing of stair railing of any height with square box made with 2 nos 25 x 25 x 5 mm angle welded (full welding) with each other (excluding cost of wood for hand rail). Considering 1 No. railing Considering 9'-9" x 2'-10"= 27.6 sft of work (a) Materials: (i) M.S. angle: 1" x 1" x 3/16" @ 1.16 lbs per rft |