Prev Next
īģŋ

 

Item No.- 21.9

 

 

 

 

Supplying, fitting and fixing 12 BWG barbed wire of 600 mm dia in fencing work @ 76 mm c/c in

 

 

 

 

spiraly fitting with 10mm dia's rod casing on 38 x 38 x 6 mm M.S. angle post

 

 

 

 

Considering 10 rft of work (a) Cost of materials

  1. 10 mm Ms Rod (@ 0.616 kg/m)

8 x 10'-0" =

80.00

rft

 

 

 

 

 

11 x 6.28' =

69.08

rft

 

 

 

 

 

=

149.08

rft

 

 

 

 

 

Add wastage 5% =

7.45

rft

 

 

 

 

 

=

156.53

rft

 

 

 

 

 

=

47.71

rm

 

 

 

 

 

=

29.39

kg @ Tk.

58.00

per kg

=

Tk.

1,704.62

  1. Barbed wire works: 12 BWG 2 ply 4 points; @ 950 rft Per cwt.

 

 

 

 

 

 

40 x 6'-4" =

253.2

rft

 

 

 

 

 

Add wastage 5% =

12.66

rft

 

 

 

 

 

=

265.86

rft

 

 

 

 

 

=

(ii) 38 mm x 38 mm x 6 mm Angle (@ 2.339 lb/rft)

6 x 1'-6" =

0.28

9.00

cwt @ Tk.

rft

6,000.00

per cwt

=

Tk.

1,680.00

Add wastage 5% =

0.45

rft

 

 

 

 

 

=

9.45

rft

 

 

 

 

 

=

(b) Fitting and consumables

(i) Electrodes

(c) Making in work-shop

  1. Welder / fabricator

22.10

30

0.5

lb @ Tk.

nos @ Tk.

nos @ Tk.

24.94

10.00

600.00

per lb

each
per day

=

=

=

Tk.

Tk. Tk.

551.17

300.00

300.00

  1. Helper

0.5

nos @ Tk.

390.00

per day

=

Tk.

195.00

(d) Carrying materials to workshop & to site

 

 

 

L.S

=

Tk.

200.00

 

 

 

 

Sub-total

=

Tk.

4,930.79

(e) Work-shop charges

 

 

 

10%

=

Tk.

493.08

(f) Ancillary work for fitting-fixing

  1. Making holes
  2. Plain concrete: (1:2:4)

2x10"X6"x6" =

2

0.415

nos @ Tk.

cft @ Tk.

12.00

17,763.63

Sub-total(a)
each
per % cft

=

=

=

Tk.
Tk.
Tk.

5,423.87

24.00

73.72

(g) Labour charge for Setting 12 BWG barbed wire hoisting the position

 

 

 

 

 

  1. Mason

0.5

nos @ Tk.

500.00

per day

=

Tk.

250.00

  1. Mason helper

0.5

nos @ Tk.

390.00

per day

=

Tk.

195.00

  1. Ordinary labour

0.5

nos @ Tk.

320.00

per day

=

Tk.

160.00

 

 

 

 

Sub-total(b)

=

Tk.

702.72

 

 

 

 

Sub-total(a+b)

=

Tk.

6,126.59

 

 

 

Profit

10.00%

=

Tk.

612.66

 

 

 

Overhead

3.50%

=

Tk.

214.43

 

 

 

 

Total

=

Tk.

6,953.68

 

Add

VAT with adjustment factor

1.06383

6.00%

=

Tk.

443.85

 

 

 

 

Grand Total

=

Tk.

7,397.53

 

 

 

 

Rate per rft

=

Tk.

739.75

 

 

 

 

Rate per rm

=

Tk.

2,427.12

 

 

Say, Tk.

2,427

.00 per meter