Prev Next


23.7.1 For ground floor

 

 

 

 

 

Rate per sft Rate per sqm

=

=

= = = =

Tk. Tk.

Tk. Tk. Tk. Tk.

146.03

1,571.28

1,572.00 18.00 28.00 32.00

23.7.2.1 Add for each additional floor up to 5th floor

23.7.2.2 Add for each additional floor for 6th floor to 9th floor

23.7.2.3 Add for each additional floor for 10th floor & above

Item No.- 23.8

 

 

 

 

 

 

 

 

 

Ferrocement sand-wich panel(cast-in-situ)

 

 

 

 

 

 

 

 

 

Considering 100 sft of work

1 Sand (F.M. 1.2) 5.00

cft

@

Tk.

 

14.00

per cft

=

Tk.

70.00

2 Sand (F.M. 2.2) 16.67

cft

@

Tk.

 

45.00

per cft

=

Tk.

750.15

3 Cement 6.67

bags

@

Tk.

 

415.00

per bags

=

Tk.

2,768.05

4 6mm dia M.S. rod 25.00

kg

@

Tk.

 

60.50

per kg

=

Tk.

1,512.50

5 21/2" EPS (density 15 x kg/m3) 21.00

cft

@

Tk.

 

90.00

per cft

=

Tk.

1,890.00

6 20 BWG galvanized (2 mesh per 25mm) 210.00

sft

@

Tk.

 

25.00

per sft

=

Tk.

5,250.00

7 G.I. wire 1.00

kg

@

Tk.

 

120.00

per kg

=

Tk.

120.00

8 Drill Bit/ Drill Machine Charge

 

 

 

 

 

LS

=

Tk.

50.00

9 Mason 2.00

nos

@

Tk.

 

500.00

each

=

Tk.

1,000.00

10 Rod binder 1.00

no

@

Tk.

 

500.00

each

=

Tk.

500.00

11 Skilled Labour 2.00

no

@

Tk.

 

390.00

each

=

Tk.

780.00

12 Helper to rod binder 1.00

no

@

Tk.

 

390.00

each

=

Tk.

390.00

13 Ordinary labour 0.75

no

@

Tk.

 

320.00

each

=

Tk.

240.00

14 Ordinary Labour for 7 days curing 0.88

no

@

Tk.

 

320.00

each

=

Tk.

280.00

15 Local carriages, storage & sundries etc. 0.24

no

@

Tk.

 

320.00

each

=

Tk.

76.80

 

 

 

 

 

 

Sub - Total

=

Tk.

15,677.50

 

 

 

 

Profit

10.00%

=

Tk.

1,567.75

 

 

 

 

Overhead

3.50%

=

Tk.

548.71

 

 

 

 

 

 

Total

=

Tk.

17,793.96

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

1,135.78

 

 

 

 

 

 

Grand Total

=

Tk.

18,929.74

 

 

 

 

 

 

Rate per sft

=

Tk.

189.30

 

 

 

 

 

 

Rate per sqm

=

Tk.

2,036.87

23.8.1 For ground floor

 

 

 

 

 

 

=

Tk.

2,037.00

23.8.2.1 Add for each additional floor up to 5th floor

 

 

 

 

 

 

=

Tk.

13.00

23.8.2.2 Add for each additional floor for 6th floor to 9th floor

 

 

 

 

 

 

=

Tk.

18.00

23.8.2.3 Add for each additional floor for 10th floor & above

 

 

 

 

 

 

=

Tk.

21.00

Item No.- 23.9

 

 

 

 

 

 

 

 

 

40 mm Ferrocement sand on slab-cement stabilization bed

 

 

 

 

 

 

 

 

 

Considering = 100 sft of work

1 Sand (F.M. 2.2) 12.50

cft

@

Tk.

 

45.00

per cft

=

Tk.

562.50

2 Cement 5.00

bags

@

Tk.

 

415.00

per bag

=

Tk.

2,075.00

3 20BWG Wire mesh (2 mesh per 25mm) 220.00

sft

@

Tk.

 

25.00

per sft

=

Tk.

5,500.00

4 Mixture Machine charge

 

 

 

 

 

LS

=

Tk.

100.00

5 Head Mason 0.10

no

@

Tk.

 

600.00

each

=

Tk.

60.00

6 Mason 1.00

no

@

Tk.

 

500.00

each

=

Tk.

500.00

7 Skilled Labour 1.00

no

@

Tk.

 

390.00

each

=

Tk.

390.00

8 Ordinary Labour for sand washing 0.20

no

@

Tk.

 

320.00

each

=

Tk.

64.00

9 Ordinary Labour for 7 days curing 0.88

no

@

Tk.

 

320.00

each

=

Tk.

281.60

10 Local carriages, storage & sundries etc. 0.20

no

@

Tk.

 

320.00

each

=

Tk.

64.00

 

 

 

 

 

 

Sub - Total

=

Tk.

9,597.10

 

 

 

 

Profit

10.00%

=

Tk.

959.71

 

 

 

 

Overhead

3.50%

=

Tk.

335.90

 

 

 

 

 

 

Total

=

Tk.

10,892.71

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

695.28

 

 

 

 

 

 

Grand Total

=

Tk.

11,587.99

 

 

 

 

 

 

Rate per sft

=

Tk.

115.88

 

 

 

 

 

 

Rate per sqm

=

Tk.

1,246.87

 

 

Say

Tk.

 

1,247 .00 per sqm