23.7.1 For ground floor |
|
|
|
|
| Rate per sft Rate per sqm | = = = = = = | Tk. Tk. Tk. Tk. Tk. Tk. | 146.03 1,571.28 1,572.00 18.00 28.00 32.00 |
23.7.2.1 Add for each additional floor up to 5th floor | |||||||||
23.7.2.2 Add for each additional floor for 6th floor to 9th floor | |||||||||
23.7.2.3 Add for each additional floor for 10th floor & above | |||||||||
Item No.- 23.8 |
|
|
|
|
|
|
|
|
|
Ferrocement sand-wich panel(cast-in-situ) |
|
|
|
|
|
|
|
|
|
Considering 100 sft of work 1 Sand (F.M. 1.2) 5.00 | cft | @ | Tk. |
| 14.00 | per cft | = | Tk. | 70.00 |
2 Sand (F.M. 2.2) 16.67 | cft | @ | Tk. |
| 45.00 | per cft | = | Tk. | 750.15 |
3 Cement 6.67 | bags | @ | Tk. |
| 415.00 | per bags | = | Tk. | 2,768.05 |
4 6mm dia M.S. rod 25.00 | kg | @ | Tk. |
| 60.50 | per kg | = | Tk. | 1,512.50 |
5 21/2" EPS (density 15 x kg/m3) 21.00 | cft | @ | Tk. |
| 90.00 | per cft | = | Tk. | 1,890.00 |
6 20 BWG galvanized (2 mesh per 25mm) 210.00 | sft | @ | Tk. |
| 25.00 | per sft | = | Tk. | 5,250.00 |
7 G.I. wire 1.00 | kg | @ | Tk. |
| 120.00 | per kg | = | Tk. | 120.00 |
8 Drill Bit/ Drill Machine Charge |
|
|
|
|
| LS | = | Tk. | 50.00 |
9 Mason 2.00 | nos | @ | Tk. |
| 500.00 | each | = | Tk. | 1,000.00 |
10 Rod binder 1.00 | no | @ | Tk. |
| 500.00 | each | = | Tk. | 500.00 |
11 Skilled Labour 2.00 | no | @ | Tk. |
| 390.00 | each | = | Tk. | 780.00 |
12 Helper to rod binder 1.00 | no | @ | Tk. |
| 390.00 | each | = | Tk. | 390.00 |
13 Ordinary labour 0.75 | no | @ | Tk. |
| 320.00 | each | = | Tk. | 240.00 |
14 Ordinary Labour for 7 days curing 0.88 | no | @ | Tk. |
| 320.00 | each | = | Tk. | 280.00 |
15 Local carriages, storage & sundries etc. 0.24 | no | @ | Tk. |
| 320.00 | each | = | Tk. | 76.80 |
|
|
|
|
|
| Sub - Total | = | Tk. | 15,677.50 |
|
|
|
| Profit | 10.00% | = | Tk. | 1,567.75 | |
|
|
|
| Overhead | 3.50% | = | Tk. | 548.71 | |
|
|
|
|
|
| Total | = | Tk. | 17,793.96 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 1,135.78 | |||
|
|
|
|
|
| Grand Total | = | Tk. | 18,929.74 |
|
|
|
|
|
| Rate per sft | = | Tk. | 189.30 |
|
|
|
|
|
| Rate per sqm | = | Tk. | 2,036.87 |
23.8.1 For ground floor |
|
|
|
|
|
| = | Tk. | 2,037.00 |
23.8.2.1 Add for each additional floor up to 5th floor |
|
|
|
|
|
| = | Tk. | 13.00 |
23.8.2.2 Add for each additional floor for 6th floor to 9th floor |
|
|
|
|
|
| = | Tk. | 18.00 |
23.8.2.3 Add for each additional floor for 10th floor & above |
|
|
|
|
|
| = | Tk. | 21.00 |
Item No.- 23.9 |
|
|
|
|
|
|
|
|
|
40 mm Ferrocement sand on slab-cement stabilization bed |
|
|
|
|
|
|
|
|
|
Considering = 100 sft of work 1 Sand (F.M. 2.2) 12.50 | cft | @ | Tk. |
| 45.00 | per cft | = | Tk. | 562.50 |
2 Cement 5.00 | bags | @ | Tk. |
| 415.00 | per bag | = | Tk. | 2,075.00 |
3 20BWG Wire mesh (2 mesh per 25mm) 220.00 | sft | @ | Tk. |
| 25.00 | per sft | = | Tk. | 5,500.00 |
4 Mixture Machine charge |
|
|
|
|
| LS | = | Tk. | 100.00 |
5 Head Mason 0.10 | no | @ | Tk. |
| 600.00 | each | = | Tk. | 60.00 |
6 Mason 1.00 | no | @ | Tk. |
| 500.00 | each | = | Tk. | 500.00 |
7 Skilled Labour 1.00 | no | @ | Tk. |
| 390.00 | each | = | Tk. | 390.00 |
8 Ordinary Labour for sand washing 0.20 | no | @ | Tk. |
| 320.00 | each | = | Tk. | 64.00 |
9 Ordinary Labour for 7 days curing 0.88 | no | @ | Tk. |
| 320.00 | each | = | Tk. | 281.60 |
10 Local carriages, storage & sundries etc. 0.20 | no | @ | Tk. |
| 320.00 | each | = | Tk. | 64.00 |
|
|
|
|
|
| Sub - Total | = | Tk. | 9,597.10 |
|
|
|
| Profit | 10.00% | = | Tk. | 959.71 | |
|
|
|
| Overhead | 3.50% | = | Tk. | 335.90 | |
|
|
|
|
|
| Total | = | Tk. | 10,892.71 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 695.28 | |||
|
|
|
|
|
| Grand Total | = | Tk. | 11,587.99 |
|
|
|
|
|
| Rate per sft | = | Tk. | 115.88 |
|
|
|
|
|
| Rate per sqm | = | Tk. | 1,246.87 |
|
| Say | Tk. |
| 1,247 .00 per sqm |
|
|
| |