Prev Next


3.142 x 4 x 1'-8"= 21 rft

Diagonally: 30 x 4'-6"= 135 rft

 

 

 

 

 

 

Horizontally:

 

 

 

 

 

 

1 x 2 x 3.44 x 1'-8"= 10.48 rft

 

 

 

 

 

 

= 166.48 rft

No. of bamboo

 

 

 

 

 

 

(@ 96'-0" split per bamboo)= 1.73 nos

(a) Muli bamboo 1.73 nos @

Tk.

120.00

each

=

Tk.

207.60

  1. G.I. wire 0.1 kg @
  2. Borrak bamboo post:

Tk.

120.00

per kg

=

Tk.

12.00

3 x 6'-0" = 18 rft @

Tk.

12.00

per rft

=

Tk.

216.00

  1. Labour (Gharami) 0.2 no @

Tk.

500.00

each

=

Tk.

100.00

 

 

 

Sub - Total

=

Tk.

535.60

 

 

Profit

10.00%

=

Tk.

53.56

 

 

Overhead

3.50%

=

Tk.

18.75

 

 

 

Total

=

Tk.

607.91

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

38.80

 

 

 

Grand Total

=

Tk.

646.71

 

 

 

Rate per No.

=

Tk.

646.71

Say,

Tk.

647 .00 each

 

 

 

 

 

 

 

 

 

 

Item No.- 25.12

 

 

 

 

 

 

Earth-work in excavation 1'-6" x 1'-6" x 1'-6" size pits for plantation of plant in/c cost of cowdung manure, loamy silty soil etc.

 

 

 

 

 

 

Considering 1'-6" x 1'-6" x 1'-6" size 10 nos pit = 33.8 cft excavation

  1. Ordinary labour for excavation 0.5 No. @
  2. Cowdung manure

(@ 1cft per pit) 10 cft @

  1. Loamy silty soil

(@ 1.2 cft Per pit) 10 cft @

  1. Ordinary labour for mixing

cowdung, soil, earth etc. 0.125 no @

Tk. Tk. Tk. Tk.

320.00

35.33

19.78

320.00

each Per cft Per cft each

= = = =

Tk. Tk. Tk. Tk.

160.00 353.30 197.80 40.00

  1. Borrak bamboo 30 rft @

Tk.

12.00

per rft

=

Tk.

360.00

  1. Incidental, sundries

 

 

LS

=

Tk.

21.33

 

 

 

Sub - Total

=

Tk.

1,132.43

 

 

Profit

10.00%

=

Tk.

113.24

 

 

Overhead

3.50%

=

Tk.

39.64

 

 

 

Total

=

Tk.

1,285.31

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

82.04

 

 

 

Grand Total

=

Tk.

1,367.35

 

 

 

Rate per pit.

=

Tk.

136.74

Say,

Tk.

137 .00 each

 

 

 

 

 

 

 

 

 

 

Item No.- 25.13

 

 

 

 

 

 

Preparation of FLOWER BEDS: Earth-work in excavation of Pits in 0.61 m / 2'-0" depth for plantation of plants.

 

 

 

 

 

 

Considering 1 x 50'-0" x4'-0"= 200 sft bed: 400 cft excavation

  1. Ordinary labour for excavation 5.5 nos @

Tk.

320.00

each

=

Tk.

1,760.00

  1. Cost of silty soil (20% of soil) 80 cft @

Tk.

19.78

Per cft

=

Tk.

1,582.40

  1. Cost of cowdung (1/6 of soil) 66.67 cft @
  2. Cost of mixing soil, cowdung

& cutted earth. 546.67 cft @

Tk. Tk.

35.33

2.54

Per cft
Per cft

=

=

Tk. Tk.

2,355.45

1,388.54

  1. Tools & plant, incidentl, sundries etc.

 

 

LS

=

Tk.

64.00

 

 

 

Sub - Total

=

Tk.

7,150.39

 

 

Profit

10.00%

=

Tk.

715.04

 

 

Overhead

3.50%

=

Tk.

250.26

 

 

 

Total

=

Tk.

8,115.69

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

518.02

 

 

 

Grand Total

=

Tk.

8,633.71