3.142 x 4 x 1'-8"= 21 rft Diagonally: 30 x 4'-6"= 135 rft |
|
|
|
|
|
|
Horizontally: |
|
|
|
|
|
|
1 x 2 x 3.44 x 1'-8"= 10.48 rft |
|
|
|
|
|
|
= 166.48 rft | ||||||
No. of bamboo |
|
|
|
|
|
|
(@ 96'-0" split per bamboo)= 1.73 nos (a) Muli bamboo 1.73 nos @ | Tk. | 120.00 | each | = | Tk. | 207.60 |
| Tk. | 120.00 | per kg | = | Tk. | 12.00 |
3 x 6'-0" = 18 rft @ | Tk. | 12.00 | per rft | = | Tk. | 216.00 |
| Tk. | 500.00 | each | = | Tk. | 100.00 |
|
|
| Sub - Total | = | Tk. | 535.60 |
|
| Profit | 10.00% | = | Tk. | 53.56 |
|
| Overhead | 3.50% | = | Tk. | 18.75 |
|
|
| Total | = | Tk. | 607.91 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 38.80 |
|
|
| Grand Total | = | Tk. | 646.71 |
|
|
| Rate per No. | = | Tk. | 646.71 |
Say, | Tk. | 647 .00 each |
|
|
| |
|
|
|
|
|
|
|
Item No.- 25.12 |
|
|
|
|
|
|
Earth-work in excavation 1'-6" x 1'-6" x 1'-6" size pits for plantation of plant in/c cost of cowdung manure, loamy silty soil etc. |
|
|
|
|
|
|
Considering 1'-6" x 1'-6" x 1'-6" size 10 nos pit = 33.8 cft excavation
(@ 1cft per pit) 10 cft @
(@ 1.2 cft Per pit) 10 cft @
cowdung, soil, earth etc. 0.125 no @ | Tk. Tk. Tk. Tk. | 320.00 35.33 19.78 320.00 | each Per cft Per cft each | = = = = | Tk. Tk. Tk. Tk. | 160.00 353.30 197.80 40.00 |
| Tk. | 12.00 | per rft | = | Tk. | 360.00 |
|
|
| LS | = | Tk. | 21.33 |
|
|
| Sub - Total | = | Tk. | 1,132.43 |
|
| Profit | 10.00% | = | Tk. | 113.24 |
|
| Overhead | 3.50% | = | Tk. | 39.64 |
|
|
| Total | = | Tk. | 1,285.31 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 82.04 |
|
|
| Grand Total | = | Tk. | 1,367.35 |
|
|
| Rate per pit. | = | Tk. | 136.74 |
Say, | Tk. | 137 .00 each |
|
|
| |
|
|
|
|
|
|
|
Item No.- 25.13 |
|
|
|
|
|
|
Preparation of FLOWER BEDS: Earth-work in excavation of Pits in 0.61 m / 2'-0" depth for plantation of plants. |
|
|
|
|
|
|
Considering 1 x 50'-0" x4'-0"= 200 sft bed: 400 cft excavation
| Tk. | 320.00 | each | = | Tk. | 1,760.00 |
| Tk. | 19.78 | Per cft | = | Tk. | 1,582.40 |
& cutted earth. 546.67 cft @ | Tk. Tk. | 35.33 2.54 | Per cft | = = | Tk. Tk. | 2,355.45 1,388.54 |
|
|
| LS | = | Tk. | 64.00 |
|
|
| Sub - Total | = | Tk. | 7,150.39 |
|
| Profit | 10.00% | = | Tk. | 715.04 |
|
| Overhead | 3.50% | = | Tk. | 250.26 |
|
|
| Total | = | Tk. | 8,115.69 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 518.02 |
|
|
| Grand Total | = | Tk. | 8,633.71 |