Add VAT with adjustment

factor

 

1.06383

Total

6.00%

=

=

Tk. Tk.

2,190.16

139.80

Grand Total Rate per No.

=

=

Tk. Tk.

2,329.96

2,329.96

 

 

 

 

Say,

Tk.

2,330 .00 each

 

 

 

26.9.3.3

Special coloured

 

 

 

 

 

 

 

 

 

 

Considering 1 No. of fixture

 

 

 

 

 

 

 

 

 

1.

Coloured wash-basin

1

no

@

Tk.

1,089.00

each

=

Tk.

1,089.00

2.

Accessories:

 

 

 

 

 

 

 

 

 

  1.  

32 mm dia PVC waste pipe

1

no

@

Tk.

150.00

each

=

Tk.

150.00

  1.  

Grating with brass coupling

1

no

@

Tk.

300.00

each

=

Tk.

300.00

  1.  

CP chain with rubber plug

1

no

@

Tk.

80.00

each

=

Tk.

80.00

3.

Fitting fixing materials:

 

 

 

 

 

 

 

 

 

(a)

Cement mortar (1:4)

 

 

 

 

 

 

 

 

 

  1.  

Cement

0.01

bag

@

Tk.

395.00

per bag

=

Tk.

3.95

  1.  

Sand (F.M. 1.2)

0.05

cft

@

Tk.

1,400.00

per % cft

=

Tk.

0.70

(b)

CI brakets

1

pair

@

Tk.

115.00

per pair

=

Tk.

115.00

4.

Labour:

 

 

 

 

 

 

 

 

 

  1.  

Plumber

0.15

no

@

Tk.

600.00

each

=

Tk.

90.00

  1.  

Skilled labour

0.2

no

@

Tk.

390.00

each

=

Tk.

78.00

  1.  

Ordinary labour

0.4

no

@

Tk.

320.00

each

=

Tk.

128.00

 

 

 

 

 

 

 

Sub - Total

=

Tk.

2,034.65

 

 

 

 

 

 

Profit

10.00%

=

Tk.

203.47

 

 

 

 

 

 

Overhead

3.50%

=

Tk.

71.21

 

 

 

 

 

 

 

Total

=

Tk.

2,309.33

 

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

147.40

 

 

 

 

 

 

 

Grand Total

=

Tk.

2,456.73

 

 

 

 

 

 

 

Rate per No.

=

Tk.

2,456.73

 

 

 

 

Say,

Tk.

2,457 .00 each

 

 

 

29.9.4

450x405x180, 7kg

 

 

 

 

 

 

 

 

 

26.9.4.1

White colour

 

 

 

 

 

 

 

 

 

 

Considering 1 No. of fixture

 

 

 

 

 

 

 

 

 

1.

Coloured wash-basin

1

no

@

Tk.

665.00

each

=

Tk.

665.00

2.

Accessories:

 

 

 

 

 

 

 

 

 

  1.  

32 mm dia PVC waste pipe

1

no

@

Tk.

150.00

each

=

Tk.

150.00

  1.  

Grating with brass coupling

1

no

@

Tk.

300.00

each

=

Tk.

300.00

  1.  

CP chain with rubber plug

1

no

@

Tk.

80.00

each

=

Tk.

80.00

3.

Fitting fixing materials:

 

 

 

 

 

 

 

 

 

(a)

Cement mortar (1:4)

 

 

 

 

 

 

 

 

 

  1.  

Cement

0.01

bag

@

Tk.

395.00

per bag

=

Tk.

3.95

  1.  

Sand (F.M. 1.2)

0.05

cft

@

Tk.

1,400.00

per % cft

=

Tk.

0.70

(b)

CI brakets

1

pair

@

Tk.

115.00

per pair

=

Tk.

115.00

4.

Labour:

 

 

 

 

 

 

 

 

 

  1.  

Plumber

0.15

no

@

Tk.

600.00

each

=

Tk.

90.00

  1.  

Skilled labour

0.2

no

@

Tk.

390.00

each

=

Tk.

78.00

  1.  

Ordinary labour

0.4

no

@

Tk.

320.00

each

=

Tk.

128.00

 

 

 

 

 

 

 

Sub - Total

=

Tk.

1,610.65

 

 

 

 

 

 

Profit

10.00%

=

Tk.

161.07

 

 

 

 

 

 

Overhead

3.50%

=

Tk.

56.37

 

 

 

 

 

 

 

Total

=

Tk.

1,828.09

 

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

116.69

 

 

 

 

 

 

 

Grand Total

=

Tk.

1,944.78

 

 

 

 

 

 

 

Rate per No.

=

Tk.

1,944.78

 

 

 

 

Say,

Tk.

1,945 .00 each

 

 

 

26.9.4.2

Coloured

 

 

 

 

 

 

 

 

 

 

Considering 1 No. of fixture

 

 

 

 

 

 

 

 

 

1.

Coloured wash-basin

1

no

@

Tk.

698.00

each

=

Tk.

698.00